21 Feb 2022 Out of 3km, 532m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
18 Feb 2022 Out of 3km, 532m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
14 Feb 2022 Out of 3km, 532m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
08 Feb 2022 Out of 3km, 520m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7
08 Feb 2022 work resumed on 13/12/2021.Out of 3km,460m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7
01 Feb 2022 work resumed on 13/12/2021.Out of 3km,460m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7
26 Jan 2022 work resumed on 13/12/2021.Out of 3km,370m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7
19 Jan 2022 work resumed on 13/12/2021.Out of 3km,317m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7
13 Jan 2022 work resumed on 13/12/2021.Out of 3km,220m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7
10 Jan 2022 work resumed on 13/12/2021.Out of 3km,204m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. Thiruvananthapuram Project AE7