Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
15 Oct 2021 | started taking trial pits and road cutting using cutter is going on from observatory hills. | Thiruvananthapuram Project AE7 | |
12 Oct 2021 | started taking trial pits and road cutting using cutter is going on from observatory hills. | Thiruvananthapuram Project AE7 | |
02 Oct 2021 | started taking trial pits for pipe laying near observatory hills. Road cutting work is scheduled on 04/10/2021 due to non availability of Road cutter. | Thiruvananthapuram Project AE7 | |
29 Sep 2021 | work started on 23/09/2021.started taking trial pits for pipe laying. | Thiruvananthapuram Project AE7 | |
25 Sep 2021 | work started on 23/09/2021.started taking trial pits for pipe laying. | Thiruvananthapuram Project AE7 | |
22 Sep 2021 | Got permission for road cutting in KRFB road on 17/09/2021.Directed Contractor to start work on 22/09/2021 but contractor informed that work can be start only on 23/09/2021 | Thiruvananthapuram Project AE7 | |
19 Sep 2021 | Got permission for road cutting in KRFB road on 17/09/2021.Directed Contractor to start work on 22/09/2021. | Thiruvananthapuram Project AE7 | |
15 Sep 2021 | The CEO,KRFB ( newly taken charge ) was contacted in person on 13.09.2021 for road cutting permission and informed that the work is held up due to pending road cutting sanction. Performa for work schedule submitted to KRFB on 14/09/2021. | Thiruvananthapuram Project AE7 | |
13 Sep 2021 | The CEO,KRFB ( newly taken charge ) was contacted in person on 13.09.2021 for road cutting permission and informed that the work is held up due to pending road cutting sanction. CEO assured to look into the matter. | Thiruvananthapuram Project AE7 | |
12 Sep 2021 | Road cutting permission from KRFB is to be obtained for starting the work. A meeting was convened by Hon'ble Minister for Transportation on 16.08.2021 with KRFB, KSEB etc. and directed to start the work urgently. In continuation of this KRFB has agreed to give permission within one week | Thiruvananthapuram Project AE7 |