31 Jul 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. A reminder letter sent from this office to get road cutting sanction in KRFB road on 06/07/2021. Thiruvananthapuram Project AE7
26 Jul 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. A reminder letter sent from this office to get road cutting sanction in KRFB road on 06/07/2021. Thiruvananthapuram Project AE7
20 Jul 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. A reminder letter sent from this office to get road cutting sanction in KRFB road on 06/07/2021. Thiruvananthapuram Project AE7
13 Jul 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. A reminder letter sent from this office to get road cutting sanction in KRFB road on 06/07/2021. Thiruvananthapuram Project AE7
06 Jul 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. Thiruvananthapuram Project AE7
30 Jun 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. Thiruvananthapuram Project AE7
28 Jun 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively after discussing with concerned MLA and Minister. Thiruvananthapuram Project AE7
22 Jun 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively within three days after discussing with concerned MLA and Minister. Thiruvananthapuram Project AE7
21 Jun 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively within three days after discussing with concerned MLA and Minister. Thiruvananthapuram Project AE7
20 Jun 2021 The scope of the work is the replacement of existing 315mm HDPE line with 350mm DI pipe for 3.5 Km.1.1 Km pipe arrived till date. Road cutting fund remitted to KRFB and PWD. The same got sanctioned in the District Coordination Committee of district collector. At first KRFB ensured to give permission after 02/05/2021(election code of conduct). But due to Covid pandemic the permission got extended till the end of lock down. But due further to delay in sanctioning the permission, SE, PHC, TVM contacted CEO, KRFB on 18.06.2021 in person. It is conveyed that permission can be given only after monsoon. But after discussion it has agreed to consider the matter as it is of urgent nature and will inform positively within three days after discussing with concerned MLA and Minister. Thiruvananthapuram Project AE7