Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Apr 2022 Out of 3km, 785m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables Thiruvananthapuram Project AE7
29 Mar 2022 Out of 3km, 767m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables Thiruvananthapuram Project AE7
25 Mar 2022 Out of 3km, 715m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables Thiruvananthapuram Project AE7
21 Mar 2022 Out of 3km, 690m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables Thiruvananthapuram Project AE7
17 Mar 2022 Out of 3km, 679m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables Thiruvananthapuram Project AE7
14 Mar 2022 Out of 3km, 650m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
07 Mar 2022 Out of 3km, 598m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
03 Mar 2022 Out of 3km, 580m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
28 Feb 2022 Out of 3km, 550m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7
24 Feb 2022 Out of 3km, 544m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. Thiruvananthapuram Project AE7