Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Apr 2022 |
Out of 3km, 785m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
29 Mar 2022 |
Out of 3km, 767m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
25 Mar 2022 |
Out of 3km, 715m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
21 Mar 2022 |
Out of 3km, 690m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
17 Mar 2022 |
Out of 3km, 679m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
14 Mar 2022 |
Out of 3km, 650m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
07 Mar 2022 |
Out of 3km, 598m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
03 Mar 2022 |
Out of 3km, 580m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
28 Feb 2022 |
Out of 3km, 550m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
24 Feb 2022 |
Out of 3km, 544m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|