Status Date |
Overall Project Status |
Project Officer |
Contact |
17 May 2022 |
Out of 3km, 990m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
09 May 2022 |
Out of 3km, 961m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
04 May 2022 |
Out of 3km, 935m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
28 Apr 2022 |
Out of 3km, 897m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
25 Apr 2022 |
Out of 3km, 873m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
20 Apr 2022 |
Out of 3km, 863m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
18 Apr 2022 |
Out of 3km, 852m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
16 Apr 2022 |
Out of 3km, 852m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
11 Apr 2022 |
Out of 3km, 841m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|
06 Apr 2022 |
Out of 3km, 827m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,Concrete road,AC pipes & heavy UG cables |
Thiruvananthapuram Project AE7 |
|