Status Date |
Overall Project Status |
Project Officer |
Contact |
06 Jan 2022 |
work resumed on 13/12/2021.Out of 3km,186m 350mm DI pipe laid till date.Work progress is slow due to presence of HDPE pipe,AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
31 Dec 2021 |
work resumed on 13/12/2021.Out of 3km,114m 350mm DI pipe laid till date.Work progress is slow due to presence of AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
27 Dec 2021 |
work resumed on 13/12/2021.Out of 3km,102m 350mm DI pipe laid till date.Work progress is slow due to presence of AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
20 Dec 2021 |
work resumed on 13/12/2021.Out of 3km,60m 350mm DI pipe laid till date.Work progress is slow due to presence of AC pipes & UG cables. |
Thiruvananthapuram Project AE7 |
|
13 Dec 2021 |
completed taking trial pits and road cutting using cutter from observatory hills to Gandhari amman kovil road. Since Contractor did'nt start work for two weeks ,a letter sent from this office for resuming work on 06/11/2021.But there was no response from contractor till date. |
Thiruvananthapuram Project AE7 |
|
06 Dec 2021 |
completed taking trial pits and road cutting using cutter from observatory hills to Gandhari amman kovil road. Since Contractor did'nt start work for two weeks ,a letter sent from this office for resuming work on 06/11/2021.But there was no response from contractor till date. |
Thiruvananthapuram Project AE7 |
|
01 Dec 2021 |
completed taking trial pits and road cutting using cutter from observatory hills to Gandhari amman kovil road. Since Contractor did'nt start work for two weeks ,a letter sent from this office for resuming work on 06/11/2021.But there was no response from contractor till date. |
Thiruvananthapuram Project AE7 |
|
27 Nov 2021 |
completed taking trial pits and road cutting using cutter from observatory hills to Gandhari amman kovil road. Since Contractor did'nt start work for two weeks ,a letter sent from this office for resuming work on 06/11/2021.But there was no response from contractor till date. |
Thiruvananthapuram Project AE7 |
|
22 Nov 2021 |
completed taking trial pits and road cutting using cutter from observatory hills to Gandhari amman kovil road. Since Contractor did'nt start work for two weeks ,a letter sent from this office for resuming work on 06/11/2021.But there was no response from contractor till date. |
Thiruvananthapuram Project AE7 |
|
19 Nov 2021 |
completed taking trial pits and road cutting using cutter from observatory hills to Gandhari amman kovil road. Since Contractor did'nt start work for two weeks ,a letter sent from this office for resuming work on 06/11/2021.But there was no response from contractor till date. |
Thiruvananthapuram Project AE7 |
|