Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Sep 2023 |
In Package 1, 2 and 3, 98% Work Completed. Package 4, 98% - KSEB Connection work in progress. Package 5, 13%- Piling work in progress.
|
Malappuram Project Dn AE5 |
|
03 Aug 2023 |
In package 1,2, and 3 98% Completed. Package 4 98% - KSEB Connection work in progress. Package 5, 11 % - Piling and pilecap Work in progress.
|
Malappuram Project Dn AE5 |
|
22 Jul 2023 |
In package 1, 2, & 3 - 98% Completed. Package 4, 97% - Flooring work under progress. Construction of compound wall under progress. Painting work in progress. KSEB Connection work in progress. Package 5, 10% - Piling Work in progress. pile load test for two piles completed.
|
Malappuram Project Dn AE5 |
|
30 Jun 2023 |
In package 1, 2, & 3 - 98% Completed. Package 4, 96%-Flooring work under progress. Construction of compound wall under progress. Painting work in progress. KSEB Connection work in progress. Package 2, 10%- Piling Work in progress. pile load test for two piles completed.
|
Malappuram Project Dn AE5 |
|
01 Jun 2023 |
In package 1, 2, & 3 - 98% Completed. Package 4, 93%- Flooring work under progress. Construction of compound wall under progress. Painting work in progress. Package 5, 9%- Piling Work in progress. |
Malappuram Project Dn AE5 |
|
18 May 2023 |
Package 5 - 50% Piling work completed. |
Malappuram Project Dn AE5 |
|
03 May 2023 |
In package 1, 2, & 3 - 98% Completed. Package 4, 92%- Flooring work under progress. Construction of compound wall under progress. Painting work in progress. Package 5, 6%- Piling Work in progress. |
Malappuram Project Dn AE5 |
|
18 Apr 2023 |
In package 1, 2 and 3- 98% completed. package 4, 90%- Flooring work under progress. Construction of compound wall under progress.Painting work in progress. package 5, 5%- Piling Work In progress. |
Malappuram Project Dn AE5 |
|
01 Apr 2023 |
In package 1, 2 and 3- 98% completed. package 4, 88%- Flooring work under progress. Construction of compound wall under progress.Painting work in progress. package 5, 4%- Piling Work In progress. |
Malappuram Project Dn AE5 |
|
14 Mar 2023 |
In Package 1, 98%- Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. In package 2, 98%- Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. In package 3, 98%- Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 Nos raw water pump erection and installation of transformers (1250 KVA, 315 KVA and 100 KVA) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. Which includes Re validation & permission of electrical inspecterate. In package 4, 87%- Flooring work under progress. Construction of compound wall under progress.Painting work in progress. In package 5, 3%- Piling Work in progress.
|
Malappuram Project Dn AE5 |
|