Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Jan 2022 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel work of First brace in progress. | Malappuram Project Dn AE3 | |
31 Dec 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel work of First brace in progress. | Malappuram Project Dn AE3 | |
21 Dec 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Column work in progress. | Malappuram Project Dn AE3 | |
16 Dec 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Column work in progress. | Malappuram Project Dn AE3 | |
09 Dec 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Column work in progress. | Malappuram Project Dn AE3 | |
02 Dec 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Plinth beam concrete work started. | Malappuram Project Dn AE3 | |
25 Nov 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Shuttering of Plinth beam work in progress. | Malappuram Project Dn AE3 | |
19 Nov 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Shuttering of Plinth beam work in progress. | Malappuram Project Dn AE3 | |
12 Nov 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Footings and pedestal coulmn work completed and earth filling work in progress. | Malappuram Project Dn AE3 | |
18 Oct 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Footing Work In Progress. | Malappuram Project Dn AE3 |