Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jan 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel work of First brace in progress. Malappuram Project Dn AE3
31 Dec 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel work of First brace in progress. Malappuram Project Dn AE3
21 Dec 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Column work in progress. Malappuram Project Dn AE3
16 Dec 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Column work in progress. Malappuram Project Dn AE3
09 Dec 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Column work in progress. Malappuram Project Dn AE3
02 Dec 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Plinth beam concrete work started. Malappuram Project Dn AE3
25 Nov 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Shuttering of Plinth beam work in progress. Malappuram Project Dn AE3
19 Nov 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Shuttering of Plinth beam work in progress. Malappuram Project Dn AE3
12 Nov 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Footings and pedestal coulmn work completed and earth filling work in progress. Malappuram Project Dn AE3
18 Oct 2021 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Footing Work In Progress. Malappuram Project Dn AE3