Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 May 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 39% - tank floor slab shuttering and reinforcement work in progress. plastering work and masonry work in progress. Malappuram Project Dn AE3
20 May 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 37% - tank floor slab shuttering and reinforcement work in progress. plastering work progress. Malappuram Project Dn AE3
11 May 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 35% - tank floor slab shuttering work in progress. plastering work progress. Malappuram Project Dn AE3
29 Apr 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 33% - tank floor slab shuttering work in progress. Malappuram Project Dn AE3
20 Apr 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 31% - column work completed. Malappuram Project Dn AE3
12 Apr 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 27% - column work in progress. Malappuram Project Dn AE3
08 Apr 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 27% - column work in progress. Malappuram Project Dn AE3
31 Mar 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 23% - concrete work of floor beam and slab completed. Malappuram Project Dn AE3
22 Mar 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 22% - steel work of floor beam and slab in progress. Malappuram Project Dn AE3
18 Mar 2022 Reasons of delay : The work for the WTP, Well, Pumphouse, Raw Water Pumping Main etc completed except Commissioning. Requires completion of dedicated power line extension to the Raw Water Pump House by KSEB. We have deposited Rs 1.21 Cr during January-21 and KSEB work started during September-21. The work is 70% completed and now slow down due to non-availability of KSEB Department supplied items like ABC cables. Constrcuction of 18LL OHSR in Niramaruthur Panchayath is under progress. For construction of 56LL OHSR in Tanur Municiplaity, the design under preparation in WASCON, which is yet to be received. Malappuram Project Dn AE3