Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Feb 2023 |
In package 1, 2 and 3- 98% completed. In package 4, 86% - Column pipe erecting progress. Flooring work under progress. Construction of compound wall under progress.Painting work in progress. In package 5, 2%- earth work excavation completed. |
Malappuram Project Dn AE5 |
|
14 Feb 2023 |
In package 1, 98 % - Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. In package 2, 98 % - Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. In package 3, 98%- Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 Nos raw water pump erection and installation of transformers (1250 KVA, 315 KVA and 100 KVA) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid RS. 1,31,747/- and RS. 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. For WTP, it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. Recently on 11/01/2023 the KSEB informed that the powerline extension work in completed. And ready to give power connection. now we start the procedure for obtaining power connection at Pump house and WTP. In package 4, 84 % - Column pipe erecting progress. Flooring work under progress. Construction of compound wall under progress.Painting work in progress. In package 5, 2 % - Earth work excavation completed.
|
Malappuram Project Dn AE5 |
|
27 Jan 2023 |
In package 1,2 & 3, 98 % Completed. In package 4, 82%- Plastering,masonry, Handrail works in progress. Column pipe errecting progress. Flooring work under progress. Construction of compound wall under progress. In package 5, 1 % Earth work excavation progress. |
Malappuram Project Dn AE5 |
|
05 Jan 2023 |
In package 1,2 and 3 98% completed. Awaiting power connection. Package 4, 79 %- Plastering,masonry, Handrail works in progress. Column pipe errecting progress. Flooring work under progress. Package 5, Earth work excavation under progress. |
Malappuram Project Dn AE5 |
|
20 Dec 2022 |
In package 1,2 and 3 98% completed. Awaiting power connection. In package 4, 77%- Plastering and masonry work in progress. Handrail works in progress. Column pipe errecting progress. In package 5, Work awarded. |
Malappuram Project Dn AE5 |
|
12 Dec 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 76%- Plastering and masonry work in progress. Handrail works in progress. Column pipe errecting progress. Package 5, Tendering work in progress. |
Malappuram Project Dn AE5 |
|
17 Nov 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. In package 4, Plastering and masonry work in progress. In package 5, Tendering work in progress. |
Malappuram Project Dn AE5 |
|
28 Oct 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. In package 4, Plastering and masonry work in progress. Tank side wall work completed. Cover slab centering work in progress. In package 5, Tendering work in progress. |
Malappuram Project Dn AE5 |
|
18 Oct 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 66%- Plastering and masonry work in progress.Sidewall work completed. In package 5, Tendering work in progress. |
Malappuram Project Dn AE5 |
|
07 Oct 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 64%- Plastering and masonry work in progress.Sidewall work completed. In package 5, Tendering work in progress. |
Malappuram Project Dn AE5 |
|