Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths

Project KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths
Project Code MLPKIIFB0117518
Type Main project
Funding Agency KIIFB
Category KIIFB
Type of scheme Water Supply
Scheme KIIFB
Description Design,construction and commissioning of 14 m Dia intake well cum pump house ,supply ,laying testing and commissioning of 800 mm DI K9 RWPM,Design,construction and commissioning of 45 MLD WTP ,25 LL capacity sump,44LL capacity OHSR,Laying of 450 mm DI K9 Clear water pumping main,distribution network and electro mechanical works etc.. Upon Completion of the project 30.89 MLD can be produced.Annual revenue will be 45099400 rupees Labour material ratio is 5:14
Status On-going
District Malappuram
Executing Office Malappuram Project Dn
AS Amount (Rs) 1000000000
AS Number GO (Rt) No.14/2017/WRD dtd 11/1/2017
TS Amount (Rs) 1000000000
TS Number GO (Rt) No.14/2017/WRD dtd 11/1/2017
Total Bill Submitted (Rs) 752073343
Total Bill Paid (Rs) 752073343
Population Benefitted 229437
Capacity in MLD 45.00
Actual Project Completion Date Date is not specified
Coverage Tanur municipality and adjoining 4 panchayaths
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 KIIFB special Investment package - WRD010-05-04-WSS to Tanur Municipality and adjoining 4 panchayaths- package 3 - Electro Mechanical Works. Project Division Malappuram
2 KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package 1 - Construction of 14 m dia Well cum pump house, Protection works and Supplying, laying, Commissioning 800 mm dia K9 RWPM. Project Division Malappuram
3 KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths-Package 2 - Construction & Commissioning of 45 MLD WTP, 44 LL OHSR, 25 LL Sump, Supply, laying, commissioning 450 mm dia DI K9 CWPM. Project Division Malappuram
4 KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package 4 - Construction of 18 LL OHSR at unniyal in Niramarathur GP Project Division Malappuram
5 KIIFB special Investment package - WRD010-05-WSS to Tanur Municipality and adjoining 4 panchayaths Package5- Construction of 56 LL OHSR at Kunnumpuram in Tanur municipality Project Division Malappuram

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Sep 2023 In Package 1, 2 and 3, 98% Work Completed. Package 4, 98% - KSEB Connection work in progress. Package 5, 13%- Piling work in progress. Malappuram Project Dn AE5
03 Aug 2023 In package 1,2, and 3 98% Completed. Package 4 98% - KSEB Connection work in progress. Package 5, 11 % - Piling and pilecap Work in progress. Malappuram Project Dn AE5
22 Jul 2023 In package 1, 2, & 3 - 98% Completed. Package 4, 97% - Flooring work under progress. Construction of compound wall under progress. Painting work in progress. KSEB Connection work in progress. Package 5, 10% - Piling Work in progress. pile load test for two piles completed. Malappuram Project Dn AE5
30 Jun 2023 In package 1, 2, & 3 - 98% Completed. Package 4, 96%-Flooring work under progress. Construction of compound wall under progress. Painting work in progress. KSEB Connection work in progress. Package 2, 10%- Piling Work in progress. pile load test for two piles completed. Malappuram Project Dn AE5
01 Jun 2023 In package 1, 2, & 3 - 98% Completed. Package 4, 93%- Flooring work under progress. Construction of compound wall under progress. Painting work in progress. Package 5, 9%- Piling Work in progress. Malappuram Project Dn AE5

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/11/2017
Scheduled date of Completion of the Project 31 Mar 2023
Expected date of Completion 08/04/2024

Processing Dates

AS Date 11 Jan 2017
TS Date 19 Jan 2017

Other details

Project Officers View