Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Oct 2022 In package 1 (98%) -Construction of well cum pump house and raw water pumping main laying got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid Rs 1,31,747/- and Rs 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. Now e tendering by KSEB for the works at well cum pump house is under progress.. But for WTP , it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charge. In package 2 (98%) - Construction of water treatment plant completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid Rs 1,31,747/- and Rs 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. Now e tendering by KSEB for the works at well cum pump house is under progress. But for WTP , it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charges. In package 3 (98%) -Construction of transformer substation, 71 HP clear water pump erection, 500 HP 3 nos raw water pump erection and installation of transformers (1250 kva, 315 kva and 100 kva) got completed except trial run and commissioning. Trial run and commissioning not done due to the lack of power connection. We have paid Rs 1,31,747/- and Rs 1,20,74157/- to KSEB for the dedicated power line extension works on 8/1/2021 for WTP and well cum pump house respectively. Now e tendering by KSEB for the works at well cum pump house is under progress. But for WTP , it is ready to connect. As the power connection at well cum pump house is not ready, we withheld the power connection procedure at WTP to avoid unnecessary power charges. In package 4 (63%) -Plastering work and masonry work in progress. Tank inner column work and sidewall work in progress. In package 5 -Tendering work in progress. Malappuram Project Dn AE5
09 Sep 2022 98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 62 % - plastering work and masonry work in progress. Tank inner column work and sidewall work in progress. Malappuram Project Dn AE5
29 Aug 2022 98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 60 % - plastering work and masonry work in progress. Tank inner column work and sidewall work in progress. Malappuram Project Dn AE5
20 Aug 2022 98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 59 % - plastering work and masonry work in progress. Tank inner column work and sidewall work in progress. Malappuram Project Dn AE5
10 Aug 2022 98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 57 % - plastering work and masonry work in progress. Tank inner column work in progress. Side wall RCC work completed. Malappuram Project Dn AE5
23 Jul 2022 98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 53 % - tank floor slab concrete work completed. plastering work and masonry work in progress. package 5, Estimate TS Approved. Malappuram Project Dn AE3
11 Jul 2022 98% of package 1,2 &3 completed. Awaiting power connection. In package 4, 51 % - tank floor slab concrete work completed. plastering work and masonry work in progress. package 5, Estimate TS Approved. Malappuram Project Dn AE3
29 Jun 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 45% - tank floor slab steel and reinforcement work in progress. plastering work and masonry work in progress. package 5, Estimate TS Approved. Malappuram Project Dn AE3
20 Jun 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 43% - tank floor slab steel and reinforcement work in progress. plastering work and masonry work in progress. Malappuram Project Dn AE3
14 Jun 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, 40% - tank floor slab shuttering and reinforcement work in progress. plastering work and masonry work in progress. Malappuram Project Dn AE3