Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Mar 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4, steel work of floor beam and slab in progress. |
Malappuram Project Dn AE3 |
|
08 Mar 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4, shuttering work in progress. |
Malappuram Project Dn AE3 |
|
28 Feb 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4, Column work in progress. |
Malappuram Project Dn AE3 |
|
19 Feb 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4, Column work in progress. |
Malappuram Project Dn AE3 |
|
12 Feb 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4, Concrete work of second brace and slab completed. |
Malappuram Project Dn AE3 |
|
05 Feb 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Shuttering work in progress. |
Malappuram Project Dn AE3 |
|
29 Jan 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel and concrete work of first floor columns completed. |
Malappuram Project Dn AE3 |
|
25 Jan 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel and concrete work of first floor columns under progress. |
Malappuram Project Dn AE3 |
|
19 Jan 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel and concrete work of first floor columns under progress. |
Malappuram Project Dn AE3 |
|
11 Jan 2022 |
98% of package 1,2 &3 completed. Awaiting power connection. Package 4 First brace and slab concrete work completed. |
Malappuram Project Dn AE3 |
|