Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Mar 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, steel work of floor beam and slab in progress. Malappuram Project Dn AE3
08 Mar 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, shuttering work in progress. Malappuram Project Dn AE3
28 Feb 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, Column work in progress. Malappuram Project Dn AE3
19 Feb 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, Column work in progress. Malappuram Project Dn AE3
12 Feb 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4, Concrete work of second brace and slab completed. Malappuram Project Dn AE3
05 Feb 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Shuttering work in progress. Malappuram Project Dn AE3
29 Jan 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel and concrete work of first floor columns completed. Malappuram Project Dn AE3
25 Jan 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel and concrete work of first floor columns under progress. Malappuram Project Dn AE3
19 Jan 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 Steel and concrete work of first floor columns under progress. Malappuram Project Dn AE3
11 Jan 2022 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 First brace and slab concrete work completed. Malappuram Project Dn AE3