Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 Sep 2021 | 98% of package 1,2 &3 completed. Awaiting power connection. Package 4 started | Malappuram Project Dn AE3 | |
25 Aug 2021 | 98% of package 1,2 &3 completed. Awaiting power connection | Malappuram Project Dn AE3 | |
30 Jul 2021 | 98% of package 1,2 &3 completed. Awaiting power connection | Malappuram Project Dn AE3 | |
12 Jul 2021 | 98% of package 1,2 &3 completed. Awaiting power connection | Malappuram Project Dn AE3 | |
01 Jul 2021 | 98% of package 1,2 &3 completed. Awaiting power connection | Malappuram Project Dn AE3 | |
16 Jun 2021 | 98% of package 1,2 &3 completed. Awaiting power connection | Malappuram Project Dn AE3 | |
14 Jun 2021 | 98% of package 1,2 &3 completed. Awaiting power connection | Malappuram Project Dn AE3 | |
01 Jun 2021 | 98% of package 1, 2 and 3 completed. 1% of package 4 completed. | Malappuram Project Dn AE3 | |
26 May 2021 | 98% of package 1, 2 and 3 completed. 1% of package 4 completed. | Malappuram Project Dn AE3 | |
05 May 2021 | 98% of package 1, 2 and 3 completed. 1% of package 4 completed. | Malappuram Project Dn AE3 |