Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Oct 2022 |
Work in progress | 79% Completed | 20/10/2022
supply- 427.66 km and Total pipe laid 309.520 km total FHTC- 8262 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 142207 m supplied and 79428.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-4998M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-13398m supplied- 13094 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 7870.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1669 No, Perumatty No.-3597, Pattenchery-2996 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
14 Oct 2022 |
Work in progress | 78% Completed | 14/10/2022
supply- 427.66 km and Total pipe laid 307.73 km total FHTC- 8107 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 142207 m supplied and 79018.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14056.69 m laid 5)110mm 8kg-4998M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 7870.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1586 No, Perumatty No.-3570, Pattenchery-2951 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
10 Oct 2022 |
Work in progress | 78% Completed | 10/10/2022
supply- 427.66 km and Total pipe laid 307.73 km total FHTC- 7977nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 142207 m supplied and 79018.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14056.69 m laid 5)110mm 8kg-4998M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 7870.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1494 No, Perumatty No.-3570, Pattenchery-2913 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
08 Oct 2022 |
Work in progress | 77% Completed | 08/10/2022
supply- 347.00 km and Total pipe laid 284.592 km total FHTC- 7921 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 78718.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 15963 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 882 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7810.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7126 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-1466 No, Perumatty No.-3570, Pattenchery-2885 { 1STbill-379,2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
29 Sep 2022 |
Work in progress | 77% Completed | 29/09/2022
supply- 347.00 km and Total pipe laid 284.592 km total FHTC- 7621 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 78718.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 15963 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 882 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7810.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7126 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-1428 No, Perumatty No.-3504, Pattenchery-2689 { 1STbill-379,2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
21 Sep 2022 |
Work in progress | 76% Completed | 21/09/2022
supply- 347.00 km and Total pipe laid 281.14 km total FHTC- 7377 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 77902.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 15109 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 882 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 3719 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7126 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-1407 No, Perumatty No.-3385, Pattenchery-2535 { 1STbill-379,2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
10 Sep 2022 |
Work in progress | 75% Completed | 10/09/2022
supply- 347.00 km and Total pipe laid 263.73 km total FHTC-7054 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 77122.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 7469 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 3653 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7126 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-1363 No, Perumatty No.-3275, Pattenchery-2416 |
Chittur Project Dn - AE 1 |
|
01 Sep 2022 |
Work in progress | 75% Completed | 01/09/2022
supply- 347.00 km and Total pipe laid 263.73 km total FHTC-7054 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 77122.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 7469 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 3653 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7126 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-1363 No, Perumatty No.-3275, Pattenchery-2416( 1st bill-379,2nd bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922-toal fhtc billed-5942 nos) |
Chittur Project Dn - AE 1 |
|
25 Aug 2022 |
Work in progress | 75% Completed | 25/08/2022 supply- 347.00 km and Total pipe laid 261.096 km total FHTC-13598 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 75370.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 6665 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 3653 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7048 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-2658 No, Perumatty No.-6412, Pattenchery-4528 |
Chittur Project Dn - AE 1 |
|
21 Aug 2022 |
Work in progress | 75% Completed | 21/08/2022
supply- 347.00 km and Total pipe laid 261.096 km total FHTC-13598 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 80867 m laid 2).90mm pvc 6kg – 112322m supplied and 75370.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 6665 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 3653 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21842.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -7048 m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 765 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-2658 No, Perumatty No.-6412, Pattenchery-4528 |
Chittur Project Dn - AE 1 |
|