Status Date |
Overall Project Status |
Project Officer |
Contact |
15 Aug 2022 |
Work in progress | 74% Completed | 15/08/2022
supply- 347.00 km and Total pipe laid 256.008 km total FHTC-6645 nos 1).90mm pvc pipe -8kg- 77034 m supplied and 78107m laid 2).90mm pvc 6kg – 112322m supplied and 74686.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5993 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied -3533 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21536.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6568m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 699 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22) FHTC Nallepilly-1329 No, Perumatty No.-3136, Pattenchery-2180 |
Chittur Project Dn - AE 1 |
|
12 Aug 2022 |
Work in progress | 74% Completed | 12/08/2022
supply- 347.00 km and Total pipe laid 256.008 km total FHTC-6557nos 1).90mm pvc pipe -8kg- 77034 m supplied and 78107m laid 2).90mm pvc 6kg – 112322m supplied and 74686.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5993 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied -3533 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21536.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6568m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 699 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed, 22)FHTC Nallepilly-1329 No, Perumatty No.-3098, Pattenchery-2130 |
Chittur Project Dn - AE 1 |
|
07 Aug 2022 |
Work in progress | 74% Completed | 07/08/2022
supply- 347.00 km and Total pipe laid 254.526 km total FHTC-6505nos 1).90mm pvc pipe -8kg- 77034 m supplied and 76949m laid 2).90mm pvc 6kg – 112322m supplied and 74524.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5993 m laid 4).110mm pvc 6 kg-15000 m supplied – 12892.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied -3533 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21476.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6466m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 699 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed , 22)FHTC Nallepilly-1329 No, Perumatty No.-3078, Pattenchery-2098 Nos=6505 |
Chittur Project Dn - AE 1 |
|
01 Aug 2022 |
Work in progress | 74% Completed | 01/08/2022
supply- 347.00 km and Total pipe laid 252.00 km total FHTC-6087nos 1).90mm pvc pipe -8kg- 77034 m supplied and 75173 m laid 2).90mm pvc 6kg – 112322m supplied and 74524.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5417 m laid 4).110mm pvc 6 kg-15000 m supplied – 12808.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11948 m laid, 8) 140 mm pvc -8 kg-4998 m supplied -3533 m laid 9)140mm pvc -10kg-300m supplied and 222 M laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21476.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6466m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 693 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed , 22)FHTC Nallepilly-1329 No, Perumatty No.-3023, Pattenchery-2034 Nos=6386 |
Chittur Project Dn - AE 1 |
|
31 Jul 2022 |
Work in progress | 74% Completed | 31/07/2022
supply- 347.00 km and Total pipe laid 240.822 km total FHTC-6087nos 1).90mm pvc pipe -8kg- 77034 m supplied and 71909 m laid 2).90mm pvc 6kg – 112322m supplied and 74524.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5417 m laid 4).110mm pvc 6 kg-15000 m supplied – 12046.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11738m laid, 8) 140 mm pvc -8 kg-4998 m supplied -2831 m laid 9)140mm pvc -10kg-300m supplied and not laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21476.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6466m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 669 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed , 22)FHTC Nallepilly-1329 No, Perumatty No.-3023, Pattenchery-2034 Nos=6386 |
Chittur Project Dn - AE 1 |
|
24 Jul 2022 |
Work in progress | 72% Completed | 24/07/2022
supply- 347.00 km and Total pipe laid 240.822 km total FHTC-6087nos 1).90mm pvc pipe -8kg- 77034 m supplied and 71909 m laid 2).90mm pvc 6kg – 112322m supplied and 74524.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5417 m laid 4).110mm pvc 6 kg-15000 m supplied – 12046.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11738m laid, 8) 140 mm pvc -8 kg-4998 m supplied -2831 m laid 9)140mm pvc -10kg-300m supplied and not laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21476.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6466m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 669 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed , 22)FHTC Nallepilly-1314No, Perumatty No.-2830, Pattenchery-1943 Nos=6087 |
Chittur Project Dn - AE 1 |
|
19 Jul 2022 |
Work in progress | 72% Completed | 19/07/2022
supply- 347.00 km and Total pipe laid 240.822 km total FHTC-6087nos 1).90mm pvc pipe -8kg- 77034 m supplied and 71909 m laid 2).90mm pvc 6kg – 112322m supplied and 74524.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 5417 m laid 4).110mm pvc 6 kg-15000 m supplied – 12046.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11738m laid, 8) 140 mm pvc -8 kg-4998 m supplied -2831 m laid 9)140mm pvc -10kg-300m supplied and not laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 32879.00 m Supplied and 21476.37 m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6466m laid 15) 350mm DI- 3588.43 m supplied and 3210.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 669 m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed , 22)FHTC Nallepilly-1314No, Perumatty No.-2830, Pattenchery-1943 Nos=6087 |
Chittur Project Dn - AE 1 |
|
15 Jul 2022 |
Work in progress | 71% Completed | 15/07/2022 Work in progress | supply- 347.00 km and Total pipe laid 240.822 km total FHTC-6087nos
1).90mm pvc pipe -8kg- 77034 m supplied and 69160 m laid 2).90mm pvc 6kg – 112322m supplied and 72945.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 2936 m laid 4).110mm pvc 6 kg-15000 m supplied – 12046.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid
6)110mm 10 kg -1556 m supplied and not laid
7).140mm pvc-6 kg-13398m supplied- 11738m laid,
8) 140 mm pvc -8 kg-4998 m supplied -2913 m laid
9)140mm pvc -10kg-300m supplied and not laid
10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid
11) 160mm 8kg 3810 m supplied -7116.50m laid
12) 200mm DI- 32879.00 m Supplied and 20970.872m laid
13) 250mm DI- 13661 m Supplied and 7846 m laid
14) 300mm DI pipe 11489m supplied -6466m laid
15) 350mm DI- 3588.43 m supplied and 3199.50 m laid
16) 450mm DI – 3720.50m supplied and 4035.60m laid
17) 500mm DI-K9 pipe-250m supplied and 282.10m laid
18) 20 mm pvc 12.50 kg 1998 m supplied
19) 80mm GI pipe-2190m supplied 642m laid
20) 125mm GI - 30 M
21). Meenakshipuram tank-painting work completed ,
22)FHTC Nallepilly-1314No, Perumatty No.-2830, Pattenchery-1943 Nos=6087
|
Chittur Project Dn - AE 1 |
|
10 Jul 2022 |
Work in progress | 70% Completed | 10/07/2022
Work in progress | 70% Completed | 10/07/2022 Work in progress | supply- 347.00 km and Total pipe laid 240 km total FHTC-6023nos 1).90mm pvc pipe -8kg- 77034 m supplied and 68656 m laid 2).90mm pvc 6kg – 112322m supplied and 72945.50 m laid 3).90mm pvc 10 kg-33741 m supplied and 2690 m laid 4).110mm pvc 6 kg-15000 m supplied – 12046.69 m laid 5)110mm 8kg-4998M supplied and 548 m laid 6)110mm 10 kg -1556 m supplied and not laid 7).140mm pvc-6 kg-13398m supplied- 11738m laid, 8) 140 mm pvc -8 kg-4998 m supplied -2913 m laid 9)140mm pvc -10kg-300m supplied and not laid 10) 160mm pvc 6 kg-12108 m supplied and 7392.50 m laid 11) 160mm 8kg 3810 m supplied -7116.50m laid 12) 200mm DI- 32879.00 m Supplied and 20970.8m laid 13) 250mm DI- 13661 m Supplied and 7846 m laid 14) 300mm DI pipe 11489m supplied -6466m laid 15) 350mm DI- 3588.43 m supplied and 3199.50 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 282.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 642m laid 20) 125mm GI - 30 M 21). Meenakshipuram tank-painting work completed , 22)FHTC Nallepilly-1314No, Perumatty No.-2787, Pattenchery-1922 Nos=6023 |
Chittur Project Dn - AE 1 |
|
09 Jul 2022 |
Work in progress | 65% Completed | 09/07/2022
Work in progress | 65% Completed | 09/07/2022 Total supply- 285 km and Total pipe laid 240 km total FHTC-5946nos ,billed FHTC -3620 No.(Nallepilly-1314 No, perumatty-2760, pattenchery-1900) |
Chittur Project Dn - AE 1 |
|