Overall Project Status

Status Date Overall Project Status Project Officer Contact
15 Nov 2024 Work has been completed | 100% Completed | 15/11/2024 Supply- 449.972 km and Total pipe laid 426 km /out of 450 km total FHTC- no 12058nos/ out of 14308 nos 1).90mm pvc pipe -8kg- 102520 m supplied and 93260.2 m laid 2).90mm pvc 6kg – 149971 m supplied and 146808.05 laid 3).90mm pvc 10 kg-55158 m supplied and 55158m laid 4).110mm pvc 6 kg- 23670 m supplied – 16366 m laid 5)110mm 8kg-7939.50 M supplied and 5249.00 m laid 6)110mm 10 kg -1554 m supplied and 285 M laid 7).140mm pvc-6 kg-17508 m supplied- 13500.60m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 7939.50 m laid 9)140mm pvc -10kg-300m supplied and 293 M laid 10) 160mm pvc 6 kg-13643.10 m supplied and 11482.60 m laid 11) 160mm 8kg 5028.10 m supplied -3810 m laid 12) 200mm DI- 38049 m Supplied and 31822.25 m laid 13) 250mm DI- 14120 m Supplied and 13311.50 m laid 14) 300mm DI pipe 11606.20m supplied -11364.50 m laid 15) 350mm DI- 3792.50 m supplied and 3690.24 m laid 16) 450mm DI – 3720.50 m supplied and 3671.70m laid 17) 500mm DI-K9 pipe-250m supplied and 246.90 m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-4236 m supplied 4084 m laid 20) 125mm GI – 551.50 M supplied 551.50 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -1063M supply and 1063m laid 23)150 mm GI -384m supplied and 264.40m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no 26 )350mm D/F-66.50 Supply-50.45 laid 27)200 d/f-45.50 supply 19.20 laid 28) 200 ms-183 supply 160 laid Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
13 Nov 2024 WORK COMPLETED Chittur Project Dn - AE 1
03 Jun 2024 Work has been completed | 100% Completed | 03/06/2024 Supply- 449.972 km and Total pipe laid 426 km /out of 450 km total FHTC- no 12058nos/ out of 14308 nos 1).90mm pvc pipe -8kg- 102520 m supplied and 93260.2 m laid 2).90mm pvc 6kg – 149971 m supplied and 146808.05 laid 3).90mm pvc 10 kg-55158 m supplied and 55158m laid 4).110mm pvc 6 kg- 23670 m supplied – 16366 m laid 5)110mm 8kg-7939.50 M supplied and 5249.00 m laid 6)110mm 10 kg -1554 m supplied and 285 M laid 7).140mm pvc-6 kg-17508 m supplied- 13500.60m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 7939.50 m laid 9)140mm pvc -10kg-300m supplied and 293 M laid 10) 160mm pvc 6 kg-13643.10 m supplied and 11482.60 m laid 11) 160mm 8kg 5028.10 m supplied -3810 m laid 12) 200mm DI- 38049 m Supplied and 31822.25 m laid 13) 250mm DI- 14120 m Supplied and 13311.50 m laid 14) 300mm DI pipe 11606.20m supplied -11364.50 m laid 15) 350mm DI- 3792.50 m supplied and 3690.24 m laid 16) 450mm DI – 3720.50 m supplied and 3671.70m laid 17) 500mm DI-K9 pipe-250m supplied and 246.90 m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-4236 m supplied 4084 m laid 20) 125mm GI – 551.50 M supplied 551.50 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -1063M supply and 1063m laid 23)150 mm GI -384m supplied and 264.40m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no 26 )350mm D/F-66.50 Supply-50.45 laid 27)200 d/f-45.50 supply 19.20 laid 28) 200 ms-183 supply 160 laid Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
03 Jun 2024 Work has been completed | 100% Completed | 03/06/2024 Supply- 449.972 km and Total pipe laid 426 km /out of 450 km total FHTC- no 12058nos/ out of 14308 nos 1).90mm pvc pipe -8kg- 102520 m supplied and 93260.2 m laid 2).90mm pvc 6kg – 149971 m supplied and 146808.05 laid 3).90mm pvc 10 kg-55158 m supplied and 55158m laid 4).110mm pvc 6 kg- 23670 m supplied – 16366 m laid 5)110mm 8kg-7939.50 M supplied and 5249.00 m laid 6)110mm 10 kg -1554 m supplied and 285 M laid 7).140mm pvc-6 kg-17508 m supplied- 13500.60m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 7939.50 m laid 9)140mm pvc -10kg-300m supplied and 293 M laid 10) 160mm pvc 6 kg-13643.10 m supplied and 11482.60 m laid 11) 160mm 8kg 5028.10 m supplied -3810 m laid 12) 200mm DI- 38049 m Supplied and 31822.25 m laid 13) 250mm DI- 14120 m Supplied and 13311.50 m laid 14) 300mm DI pipe 11606.20m supplied -11364.50 m laid 15) 350mm DI- 3792.50 m supplied and 3690.24 m laid 16) 450mm DI – 3720.50 m supplied and 3671.70m laid 17) 500mm DI-K9 pipe-250m supplied and 246.90 m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-4236 m supplied 4084 m laid 20) 125mm GI – 551.50 M supplied 551.50 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -1063M supply and 1063m laid 23)150 mm GI -384m supplied and 264.40m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no 26 )350mm D/F-66.50 Supply-50.45 laid 27)200 d/f-45.50 supply 19.20 laid 28) 200 ms-183 supply 160 laid Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
30 May 2024 Supply- 449.972 km and Total pipe laid 426 km /out of 450 km total FHTC- no 12058nos/ out of 14308 nos 1).90mm pvc pipe -8kg- 102520 m supplied and 93260.2 m laid 2).90mm pvc 6kg – 149971 m supplied and 146808.05 laid 3).90mm pvc 10 kg-55158 m supplied and 55158m laid 4).110mm pvc 6 kg- 23670 m supplied – 16366 m laid 5)110mm 8kg-7939.50 M supplied and 5249.00 m laid 6)110mm 10 kg -1554 m supplied and 285 M laid 7).140mm pvc-6 kg-17508 m supplied- 13500.60m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 7939.50 m laid 9)140mm pvc -10kg-300m supplied and 293 M laid 10) 160mm pvc 6 kg-13643.10 m supplied and 11482.60 m laid 11) 160mm 8kg 5028.10 m supplied -3810 m laid 12) 200mm DI- 38049 m Supplied and 31822.25 m laid 13) 250mm DI- 14120 m Supplied and 13311.50 m laid 14) 300mm DI pipe 11606.20m supplied -11364.50 m laid 15) 350mm DI- 3792.50 m supplied and 3690.24 m laid 16) 450mm DI – 3720.50 m supplied and 3671.70m laid 17) 500mm DI-K9 pipe-250m supplied and 246.90 m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-4236 m supplied 4084 m laid 20) 125mm GI – 551.50 M supplied 551.50 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -1063M supply and 1063m laid 23)150 mm GI -384m supplied and 264.40m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no 26 )350mm D/F-66.50 Supply-50.45 laid 27)200 d/f-45.50 supply 19.20 laid 28) 200 ms-183 supply 160 laid Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
06 May 2024 work completed Work in progress | 99% Completed | 06/05/2024 Supply- 449.972 km and Total pipe laid 426 km /out of 450 km total FHTC- no 12058nos/ out of 14308 nos 1).90mm pvc pipe -8kg- 102520 m supplied and 93260.2 m laid 2).90mm pvc 6kg – 149971 m supplied and 146808.05 laid 3).90mm pvc 10 kg-55158 m supplied and 55158m laid 4).110mm pvc 6 kg- 23670 m supplied – 16366 m laid 5)110mm 8kg-7939.50 M supplied and 5249.00 m laid 6)110mm 10 kg -1554 m supplied and 285 M laid 7).140mm pvc-6 kg-17508 m supplied- 13500.60m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 7939.50 m laid 9)140mm pvc -10kg-300m supplied and 293 M laid 10) 160mm pvc 6 kg-13643.10 m supplied and 11482.60 m laid 11) 160mm 8kg 5028.10 m supplied -3810 m laid 12) 200mm DI- 38049 m Supplied and 31822.25 m laid 13) 250mm DI- 14120 m Supplied and 13311.50 m laid 14) 300mm DI pipe 11606.20m supplied -11364.50 m laid 15) 350mm DI- 3792.50 m supplied and 3690.24 m laid 16) 450mm DI – 3720.50 m supplied and 3671.70m laid 17) 500mm DI-K9 pipe-250m supplied and 246.90 m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-4236 m supplied 4084 m laid 20) 125mm GI – 551.50 M supplied 551.50 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -1063M supply and 1063m laid 23)150 mm GI -384m supplied and 264.40m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no 26 )350mm D/F-66.50 Supply-50.45 laid 27)200 d/f-45.50 supply 19.20 laid 28) 200 ms-183 supply 160 laid Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
02 May 2024 Work in progress | 96% Completed | 02/05/2024 Supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
25 Apr 2024 Work in progress | 96% Completed | 25/04/2024 supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
19 Apr 2024 Work in progress | 96% Completed | 19/04/2024 supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1
11 Apr 2024 Work in progress | 96% Completed | 11/04/2024 supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No Chittur Project Dn - AE 1