Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Aug 2023 |
Work in progress | 95% Completed | 12/08/2023
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 11528nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3499No,/out of 4176 no Perumatty No.-4222/out of 4744 nos pattenchery-3807/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
03 Aug 2023 |
Work in progress | 95% Completed | 03/08/2023
supply- 440 km and Total pipe laid 431.278 km /out of 447km total FHTC- no 11361nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3403No,/out of 4176 no Perumatty No.-4188/out of 4744 nos pattenchery-3770/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
20 Jul 2023 |
Work in progress | 95% Completed | 20/07/2023
supply- 440 km and Total pipe laid 429.352 km /out of 447km total FHTC- no 11120 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 91314 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3356 No,/out of 4176 no Perumatty No.-4123/out of 4744 nos pattenchery-3641/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
13 Jul 2023 |
Work in progress | 94% Completed | 13/07/2023
supply- 427.66 km and Total pipe laid 427 km /out of 440km total FHTC- no 11120 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 92286.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3356 No,/out of 4176 no Perumatty No.-4123/out of 4744 nos pattenchery-3641/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
06 Jul 2023 |
Work in progress | 95% Completed | 06/07/2023
supply- 427.66 km and Total pipe laid 424.777 km /out of 440km total FHTC- no 11115 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 89286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3356 No,/out of 4176 no Perumatty No.-4118/out of 4744 nos pattenchery-3641/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
29 Jun 2023 |
Work in progress | 94% Completed | 29/06/2023
supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10937 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3252 No,/out of 4176 no Perumatty No.-4053/out of 4744 nos pattenchery-3632/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
23 Jun 2023 |
Work in progress | 94% Completed | 23/06/2023
supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10937 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3252 No,/out of 4176 no Perumatty No.-4053/out of 4744 nos pattenchery-3632/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
15 Jun 2023 |
Work in progress | 94% Completed | 15/06/2023
supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10937 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3252 No,/out of 4176 no Perumatty No.-4053/out of 4744 nos pattenchery-3632/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
08 Jun 2023 |
Work in progress | 94% Completed | 08/06/2023
supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10916 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3241 No,/out of 4176 no Perumatty No.-4043 /out of 4744 nos pattenchery-3632/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
02 Jun 2023 |
Work in progress | 94% Completed | 02/06/2023
supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10893nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3238No,/out of 4176 no Perumatty No.-4034/out of 4744 nos pattenchery-3621/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|