Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Mar 2022 Work in progress | 43% Completed | 21/03/2022 Total supply- 199.34km and Total 170.00km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 56931.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 53205 m laid 3).90mm pvc 10 kg-12.996km supplied and 10403.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2839.50 m laid 7).250mm DI- 13494 m Supplied and 1714.50m laid 8). 200mm DI- 22097m Supplied and 9486.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 3292 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 5334m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 492m laid 15) 300mm DI pipe 6989 m supplied -2718.50m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-366 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed Total connection -4075 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-968 No, Perumatty No.-2115, Pattenchery-1109 Nos total 4202nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
17 Mar 2022 Work in progress | 43% Completed | 17/03/2022 1). Total supply- 199.34 km 2). Total 170.00 km pipe laid 3).Meenakshipuram tank-painting work completed 4).Total connection -4202 Nos connection provided 5)TOTAL BILLED -3200 Nos billed Chittur Project Dn - AE 1
16 Mar 2022 Work in progress | 42% Completed | 16/03/2022 Total supply- 197.84km and Total 169.807km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 56931.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 53205 m laid 3).90mm pvc 10 kg-12.996km supplied and 10403.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2839.50 m laid 7).250mm DI- 13494 m Supplied and 1714.50m laid 8). 200mm DI- 22097m Supplied and 9486.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 3292 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 5334m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 492m laid 15) 300mm DI pipe 6989 m supplied -2718.50m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-366 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed Total connection -4075 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-968 No, Perumatty No.-2115, Pattenchery-1109 Nos total 4202nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
13 Mar 2022 Work in progress | 41% Completed | 13/03/2022 Total supply- 197.84km and Total 159.807km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 56931.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 53205 m laid 3).90mm pvc 10 kg-12.996km supplied and 10403.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2839.50 m laid 7).250mm DI- 13494 m Supplied and 1714.50m laid 8). 200mm DI- 22097m Supplied and 9486.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 3292 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 5334m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 492m laid 15) 300mm DI pipe 6989 m supplied -2718.50m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-366 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed Total connection -4075 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-968 No, Perumatty No.-2115, Pattenchery-1109 Nos total 4202nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
08 Mar 2022 Work in progress | 41% Completed | 08/03/2022 Total supply- 197.84km and Total 159.807km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 56931.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 53205 m laid 3).90mm pvc 10 kg-12.996km supplied and 10403.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2839.50 m laid 7).250mm DI- 13494 m Supplied and 1714.50m laid 8). 200mm DI- 22097m Supplied and 9486.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 3292 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 5334m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 492m laid 15) 300mm DI pipe 6989 m supplied -2718.50m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-366 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed Total connection -4075 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-968 No, Perumatty No.-2088, Pattenchery-1019 Nos total 4075nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
02 Mar 2022 Work in progress | 41% Completed | 02/03/2022 Total supply- 197.84km and Total 150.938km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 55005.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 52896 m laid 3).90mm pvc 10 kg-12.996km supplied and 7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2663.5 m laid 7).250mm DI- 13494 m Supplied and 802M laid 8). 200mm DI- 22097m Supplied and 9402.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 2980.00 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 4230.00m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 399m laid 15) 300mm DI pipe 6989 m supplied -2203.50m laid 16) 140 mm pvc -8 kg-1710 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-318 m laid Meenakshipuram tank-painting work completed Total connection -3774 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-950 No, Perumatty No.-2062, Pattenchery-966 Nos total 3978 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
27 Feb 2022 Work in progress | 41% Completed | 27/02/2022 Total supply- 197.84km and Total 150.938km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 55005.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 52896 m laid 3).90mm pvc 10 kg-12.996km supplied and 7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2663.5 m laid 7).250mm DI- 13494 m Supplied and 802M laid 8). 200mm DI- 22097m Supplied and 9402.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 2980.00 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 4230.00m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 399m laid 15) 300mm DI pipe 6989 m supplied -2203.50m laid 16) 140 mm pvc -8 kg-1710 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-318 m laid Meenakshipuram tank-painting work completed Total connection -3774 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-950 No, Perumatty No.-1974, Pattenchery-850 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
21 Feb 2022 Work in progress | 41% Completed | 21/02/2022 Total supply- 197.84km and Total 150.938km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 55005.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 52896 m laid 3).90mm pvc 10 kg-12.996km supplied and 7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2074.10m laid 6).350mm DI- 3588.43 m supplied and 2663.5 m laid 7).250mm DI- 13494 m Supplied and 802M laid 8). 200mm DI- 22097m Supplied and 9402.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 2980.00 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 4230.00m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 399m laid 15) 300mm DI pipe 6989 m supplied -2203.50m laid 16) 140 mm pvc -8 kg-1710 m 17)160mm 8kg 1998 m supplied 18)110mm 8kg-318 m laid Meenakshipuram tank-painting work completed Total connection -3774 Nos connection provided (non tagged) (1594 Nos tagged)Total Nallepilly-950 No, Perumatty No.-1974, Pattenchery-850 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) Chittur Project Dn - AE 1
13 Feb 2022 Work in progress | 41% Completed | 13/02/2022 Total supply- 176.285km and Total 148.871km pipe laid 1).90mm pvc pipe -8kg- 38.160 km supplied and 53535.80mlaid 2).90mm pvc 6kg- 61.407km supplied and 52407 m laid 3).90mm pvc 10 kg-12.996km supplied and 7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3678.m supplied and 2074.10m laid 6).350mm DI- 2981 m supplied and 2663.5 m laid 7).250mm DI- 13494m Supplied and 613M laid 8). 200mm DI- 13818 m Supplied and 9066.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-5910 m supplied – 2980.00 m laid 11).160mm pvc 6 kg-10404m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--399m laid 15) 300mm DI pipe 6479m supplied -2203.50m laid 16) 140 mm pvc -8 kg-1746 m 17)160mm 8kg 1998m supplied Meenakshipuram tank-painting work in progress. Total connection -3259 Nos connection provided (non tagged)Total Nallepilly-113 No, Perumatty No.-1141, Pattenchery-182 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos)Nallepilly-916,perumatty-1730,pattenchery-705,non taged total-3351 FHTC ,tagged 1536 FHTC Chittur Project Dn - AE 1
06 Feb 2022 Work in progress | 40% Completed | 06/02/2022 Total 143.779km pipe laid 1).90mm pvc pipe -8kg- 37.098 km supplied and 52389.80mlaid 2).90mm pvc 6kg- 56.907km supplied and 50678.00 m laid 3).90mm pvc 10 kg-12.996km supplied and 7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 2656 .50m supplied and 2074.10m laid 6).350mm DI- 2882 m supplied and 2658 m laid 7).250mm DI- 12252m Supplied and 27.50M laid 8). 200mm DI- 12336m Supplied and 8248.5 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-9000m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--369.00m laid 15) 300mm DI pipe 6479m supplied -1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-painting work in progress. Total connection -3259 Nos connection provided (non tagged)Total Nallepilly-113 No, Perumatty No.-1141, Pattenchery-182 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos)Nallepilly-916,perumatty-1730,pattenchery-705,non taged total-3351 FHTC ,tagged 1536 FHTC Chittur Project Dn - AE 1