Status Date |
Overall Project Status |
Project Officer |
Contact |
08 Jul 2022 |
Work in progress | 65% Completed | 08/07/2022
Work in progress | 62% Completed | 05/07/2022 Total supply- 285 km and Total pipe laid 240 km total FHTC-5946nos 1).90mm pvc pipe -8kg- 51.916 km supplied and 66.358 m laid 2).90mm pvc 6kg – 62.907km supplied and 72945.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 2030 m laid 5). 450mm DI – 3720.50m supplied and 3541.60m laid 4).500mm DI-K9 pipe-250m supplied and 282.10m laid 6).350mm DI- 3588.43 m supplied and 3199.50 m laid 7).250mm DI- 13661 m Supplied and 7846 m laid 8). 200mm DI- 28154 m Supplied and 20056.30m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 11852 m laid 11).160mm pvc 6 kg-10806 m supplied and 7302.50 m laid 12).140mm pvc-6 kg-3300 m supplied- 11738m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 642m laid 15) 300mm DI pipe 11489m supplied -6370.00m laid 16) 140 mm pvc -8 kg-2913 m 17)160mm 8kg 1998 m supplied -714m laid 18)110mm 8kg-548 m laid 19).125mm GI - 30 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1314No, Perumatty No.-2760, Pattenchery-1900 Nos=5974 |
Chittur Project Dn - AE 1 |
|
07 Jul 2022 |
Work in progress | 63% Completed | 07/07/2022
Work in progress | 62% Completed | 05/07/2022 Total supply- 283 km and Total pipe laid 237 km total FHTC-5946nos 1).90mm pvc pipe -8kg- 51.916 km supplied and 66.358 m laid 2).90mm pvc 6kg – 62.907km supplied and 72945.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 2030 m laid 5). 450mm DI – 3720.50m supplied and 3541.60m laid 4).500mm DI-K9 pipe-250m supplied and 282.10m laid 6).350mm DI- 3588.43 m supplied and 3199.50 m laid 7).250mm DI- 13661 m Supplied and 7846 m laid 8). 200mm DI- 28154 m Supplied and 20056.30m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 11852 m laid 11).160mm pvc 6 kg-10806 m supplied and 7302.50 m laid 12).140mm pvc-6 kg-3300 m supplied- 11738m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 642m laid 15) 300mm DI pipe 11489m supplied -6370.00m laid 16) 140 mm pvc -8 kg-2913 m 17)160mm 8kg 1998 m supplied -714m laid 18)110mm 8kg-548 m laid 19).125mm GI - 30 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1314No, Perumatty No.-2760, Pattenchery-1900 Nos=5974 |
Chittur Project Dn - AE 1 |
|
05 Jul 2022 |
Work in progress | 62% Completed | 05/07/2022
Total supply- 283 km and Total pipe laid 237 km total FHTC-5946nos 1).90mm pvc pipe -8kg- 51.916 km supplied and 66.358 m laid 2).90mm pvc 6kg – 62.907km supplied and 72945.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 2030 m laid 5). 450mm DI – 3720.50m supplied and 3541.60m laid 4).500mm DI-K9 pipe-250m supplied and 282.10m laid 6).350mm DI- 3588.43 m supplied and 3199.50 m laid 7).250mm DI- 13661 m Supplied and 7846 m laid 8). 200mm DI- 28154 m Supplied and 20056.30m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 11852 m laid 11).160mm pvc 6 kg-10806 m supplied and 7302.50 m laid 12).140mm pvc-6 kg-3300 m supplied- 11738m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 642m laid 15) 300mm DI pipe 11489m supplied -6370.00m laid 16) 140 mm pvc -8 kg-2913 m 17)160mm 8kg 1998 m supplied -714m laid 18)110mm 8kg-548 m laid 19).125mm GI - 30 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1314No, Perumatty No.-2752, Pattenchery-1880 Nos |
Chittur Project Dn - AE 1 |
|
27 Jun 2022 |
Work in progress | 60% Completed | 27/06/2022
Total supply- 270km and Total pipe laid 229.631km total FHTC-5834nos 1).90mm pvc pipe -8kg- 44.716 km supplied and 64060.80 m laid 2).90mm pvc 6kg – 62.907km supplied and 71339.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 1616 m laid 5). 450mm DI – 3720.50m supplied and 3047.60m laid 4).500mm DI-K9 pipe-250m supplied and 184.10m laid 6).350mm DI- 3588.43 m supplied and 3199.50 m laid 7).250mm DI- 13661 m Supplied and 7846 m laid 8). 200mm DI- 22097m Supplied and 19213.80m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 11660 m laid 11).160mm pvc 6 kg-10806 m supplied and 7212.50m laid 12).140mm pvc-6 kg-3300 m supplied- 11528m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 624 m laid 15) 300mm DI pipe 11489m supplied -6724.00m laid 16) 140 mm pvc -8 kg-2913 m 17)160mm 8kg 1998 m supplied -312m laid 18)110mm 8kg-548 m laid 19).125mm GI - 24 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1306No, Perumatty No.-2712, Pattenchery-1816 Nos |
Chittur Project Dn - AE 1 |
|
22 Jun 2022 |
Total supply- 270km and Total pipe laid 229.631km total FHTC-5770nos
1).90mm pvc pipe -8kg- 44.716 km supplied and 64060.80 m laid
2).90mm pvc 6kg – 62.907km supplied and 71339.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 1616 m laid
5). 450mm DI – 3720.50m supplied and 3047.60m laid 4).500mm DI-K9 pipe-250m supplied and 184.10m laid 6).350mm DI- 3588.43 m supplied and 3199.50 m laid 7).250mm DI- 13661 m Supplied and 7846 m laid
8). 200mm DI- 22097m Supplied and 19213.80m laid
9).20 mm pvc 12.50 kg 1998 m supplied
10).110mm pvc 6 kg-7578 m supplied – 11660 m laid 11).160mm pvc 6 kg-10806 m supplied and 7212.50m laid 12).140mm pvc-6 kg-3300 m supplied- 11528m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 624 m laid
15) 300mm DI pipe 11489m supplied -6724.00m laid
16) 140 mm pvc -8 kg-2913 m
17)160mm 8kg 1998 m supplied -312m laid
18)110mm 8kg-548 m laid 19).125mm GI - 24 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1306No, Perumatty No.-2684, Pattenchery-1780 Nos
|
Chittur Project Dn - AE 1 |
|
16 Jun 2022 |
Work in progress | 58% Completed | 16/06/2022
Total supply- 270km and Total pipe laid 220.262 km total FHTC-5711 nos 1).90mm pvc pipe -8kg- 44.716 km supplied and 64060.80 m laid 2).90mm pvc 6kg – 62.907km supplied and 67461.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 1616 m laid 5). 450mm DI – 3720.50m supplied and 3047.60m laid 4).500mm DI-K9 pipe-250m supplied and 184.10m laid 6).350mm DI- 3588.43 m supplied and 3193.50 m laid 7).250mm DI- 13661 m Supplied and 7366 m laid 8). 200mm DI- 22097m Supplied and 17405.00m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 5588 m laid 11).160mm pvc 6 kg-10806 m supplied and 7212.50m laid 12).140mm pvc-6 kg-3300 m supplied- 6872m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 624 m laid 15) 300mm DI pipe 11489m supplied -6724.00m laid 16) 140 mm pvc -8 kg-2913 m 17)160mm 8kg 1998 m supplied -312m laid 18)110mm 8kg-548 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1295 No, Perumatty No.-2654, Pattenchery-1762 Nos |
Chittur Project Dn - AE 1 |
|
30 May 2022 |
Work in progress | 54% Completed | 30/05/2022
Total supply- 210km and Total 200.782km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 63556.80 m laid 2).90mm pvc 6kg – 62.907km supplied and 60433.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 17442m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2475.10m laid 6).350mm DI- 3588.43 m supplied and 3193.50 m laid 7).250mm DI- 13661 m Supplied and 5649 m laid 8). 200mm DI- 22097m Supplied and 12745.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 4172 m laid 11).160mm pvc 6 kg-10806 m supplied and 7212.50m laid 12).140mm pvc-6 kg-3300 m supplied- 6792m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 576 m laid 15) 300mm DI pipe 11489m supplied -5471.00m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied -258m laid 18)110mm 8kg-548 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1251 No, Perumatty No.-2580, Pattenchery-1696 Nos total -5527nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400,4 TH BILL-420 No TOTAL-3620 Nos billed) |
Chittur Project Dn - AE 1 |
|
30 May 2022 |
Total supply- 210km and Total 200.782km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 63556.80 m laid 2).90mm pvc 6kg – 62.907km supplied and 60433.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 17442m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2475.10m laid 6).350mm DI- 3588.43 m supplied and 3193.50 m laid 7).250mm DI- 13661 m Supplied and 5649 m laid 8). 200mm DI- 22097m Supplied and 12745.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 4172 m laid 11).160mm pvc 6 kg-10806 m supplied and 7212.50m laid 12).140mm pvc-6 kg-3300 m supplied- 6792m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 576 m laid 15) 300mm DI pipe 11489m supplied -5471.00m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied -258m laid 18)110mm 8kg-548 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1251 No, Perumatty No.-2580, Pattenchery-1696 Nos total -5527nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400,4 TH BILL-420 No TOTAL-3620 Nos billed) |
Chittur Project Dn - AE 1 |
|
30 May 2022 |
Work in progress | 54% Completed | 30/05/2022
Total supply- 210km and Total 200.782km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 63556.80 m laid 2).90mm pvc 6kg – 62.907km supplied and 60433.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 17442m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2475.10m laid 6).350mm DI- 3588.43 m supplied and 3193.50 m laid 7).250mm DI- 13661 m Supplied and 5649 m laid 8). 200mm DI- 22097m Supplied and 12745.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 4172 m laid 11).160mm pvc 6 kg-10806 m supplied and 7212.50m laid 12).140mm pvc-6 kg-3300 m supplied- 6792m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 576 m laid 15) 300mm DI pipe 11489m supplied -5471.00m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied -258m laid 18)110mm 8kg-548 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed ,FHTC Nallepilly-1251 No, Perumatty No.-2580, Pattenchery-1696 Nos total -5527nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400,4 TH BILL-420 No TOTAL-3620 Nos billed) |
Chittur Project Dn - AE 1 |
|
23 May 2022 |
Work in progress | 53% Completed | 23/05/2022
Total supply- 199.049km and Total 199.355km pipe laid 1).90mm pvc pipe -8kg- 44.716 km supplied and 63484.80 m laid 2).90mm pvc 6kg – 62.907km supplied and 60133.50 m laid 3).90mm pvc 10 kg-12.996km supplied and 17442m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI – 3720.50m supplied and 2475.10m laid 6).350mm DI- 3588.43 m supplied and 3193.50 m laid 7).250mm DI- 13661 m Supplied and 5649 m laid 8). 200mm DI- 22097m Supplied and 12542 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-7578 m supplied – 3872 m laid 11).160mm pvc 6 kg-10806 m supplied and 7116.50m laid 12).140mm pvc-6 kg-3300 m supplied- 6336m laid, 13).160mm pvc -10kg- 1002 m supplied 6162.50m laid 14).80mm GI pipe-2190m supplied 576 m laid 15) 300mm DI pipe 11489m supplied -5471.00m laid 16) 140 mm pvc -8 kg-2331 m 17)160mm 8kg 1998 m supplied -258m laid 18)110mm 8kg-548 m laid 19).125mm GI -12 M Meenakshipuram tank-painting work completed Total connection -4813 Nos connection provided. Total Nallepilly-1129 No, Perumatty No.-2525, Pattenchery-1642 Nos total -5296 nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,3rd bill-1400 TOTAL-3200 Nos billed) |
Chittur Project Dn - AE 1 |
|