Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Feb 2022 |
Work in progress | 40% Completed | 05/02/2022
Total 143.779km pipe laid 1).90mm pvc pipe -8kg- 37.098 km supplied and 52389.80mlaid 2).90mm pvc 6kg- 64.917km supplied and 50678.00 m laid 3).90mm pvc 10 kg-12.996km supplied and 7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 2656 .50m supplied and 2074.10m laid 6).350mm DI- 2882 m supplied and 2658 m laid 7).250mm DI- 12252m Supplied and 27.50M laid 8). 200mm DI- 12336m Supplied and 8248.5 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-9000m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--369.00m laid 15) 300mm DI pipe 6479m supplied -1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-painting work in progress. Total connection -3259 Nos connection provided (non tagged)Total Nallepilly-113 No, Perumatty No.-1141, Pattenchery-182 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos)Nallepilly-916,perumatty-1730,pattenchery-705,non taged total-3351 FHTC ,tagged 1536 FHTC |
Chittur Project Dn - AE 1 |
|
02 Feb 2022 |
Letter given to the contractor for speed up the work on 18.01.2022 |
Chittur Project Dn - AE 1 |
|
02 Feb 2022 |
Work in progress | 36% Completed | 02/02/2022
Total 143.779km pipe laid 1).90mm pvc pipe -8kg- 37.098 km supplied and 52389.80mlaid 2).90mm pvc 6kg- 35.600km supplied and 50678.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2658 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 8248.5 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--369.00m laid 15) 300mm DI –PIPE-1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-painting work in progress. Total connection -3259 Nos connection provided (non tagged)Total Nallepilly-113 No, Perumatty No.-1141, Pattenchery-182 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos)Nallepilly-916,perumatty-1730,pattenchery-705,non taged total-3351 FHTC ,tagged 1536 FHTC |
Chittur Project Dn - AE 1 |
|
31 Jan 2022 |
Work in progress | 36% Completed | 31/01/2022
TOotal 141.km laid ,Nallepilly-907,perumatty-1730,pattenchery-705,non taged total-3342 FHTC ,tagged 1506 FHTC |
Chittur Project Dn - AE 1 |
|
24 Jan 2022 |
Work in progress | 36% Completed | 24/01/2022
Total 141.742 km pipe laid 1).90mm pvc pipe -8kg- 37.098 km supplied and 51297.80m laid 2).90mm pvc 6kg- 35.600km supplied and 50186.00 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2658 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 7795.50 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--369.00m laid 15) 300mm DI –PIPE-1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-painting work in progress. Total connection -3259 Nos connection provided (non tagged)Total Nallepilly-113 No, Perumatty No.-1141, Pattenchery-182 Nos total 1436 nos of FHTC provided (tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 No |
Chittur Project Dn - AE 1 |
|
20 Jan 2022 |
Work in progress | 35% Completed | 20/01/2022
Total 141.742 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 49899.80km laid 2).90mm pvc 6kg- 35.600km supplied and 48056 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2345.50 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 6388.00 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--277.00m laid 15) 300mm DI –PIPE-1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-painting work in progress. Total connection -3170 Nos connection provided (non tagged)Total Nallepilly-113 No, Perumatty No.-1141, Pattenchery-121 Nos total 1375 nos of FHTC provided(tagged) ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos) |
Chittur Project Dn - AE 1 |
|
12 Jan 2022 |
Work in progress | 34% Completed | 12/01/2022
200 MM DI K9 -pipe line laying work in progress |
Chittur Project Dn - AE 1 |
|
10 Jan 2022 |
Work in progress | 34% Completed | 10/01/2022
Total 141.742 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 49899.80km laid 2).90mm pvc 6kg- 35.600km supplied and 48056 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2345.50 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 6388.00 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--277.00m laid 15) 300mm DI –PIPE-1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-plastering work in progress. Total connection -2965 Nos connection provided Total Nallepilly-108 No, Perumatty No.-1088, Pattenchery-121 Nos total 1317 nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos) |
Chittur Project Dn - AE 1 |
|
05 Jan 2022 |
Work in progress | 34% Completed | 05/01/2022
Total 141.742 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 49899.80km laid 2).90mm pvc 6kg- 35.600km supplied and 48056 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2345.50 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 6388.00 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--277.00m laid 15) 300mm DI –PIPE-1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-plastering work in progress. Total connection -2965 Nos connection provided Total Nallepilly-108 No, Perumatty No.-1088, Pattenchery-121 Nos total 1317 nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos) |
Chittur Project Dn - AE 1 |
|
02 Jan 2022 |
Work in progress | 34% Completed | 02/01/2022
Total 141.742 km pipe laid 1).90mm pvc pipe -8kg- 37.098 k m supplied and 49899.80km laid 2).90mm pvc 6kg- 35.600km supplied and 48056 m laid 3).90mm pvc 10 kg-7646.00m laid 4).500mm DI-K9 pipe-250m supplied and 184.50 m laid 5). 450mm DI - 1650 m supplied and 2074.10m laid 6).350mm DI- 1562 m supplied and 2345.50 m laid 7).250mm DI- Supplied and 27.50M laid 8). 200mm DI- 1749m Supplied and 6388.00 m laid 9).20 mm pvc 12.50 kg 1998 m supplied 10).110mm pvc 6 kg-3000m supplied – 2980.00 m laid 11).160mm pvc 6 kg-4352.00m supplied and 7116.50m laid 12).140mm pvc-6 kg-3000m supplied- 4230.00m laid, 13).160mm pvc -10kg-6162.50m laid 14).80mm GI pipe--277.00m laid 15) 300mm DI –PIPE-1971.50m laid 16) 140 mm pvc -8 kg-384 m Meenakshipuram tank-plastering work in progress. Total connection -2965 Nos connection provided Total Nallepilly-108 No, Perumatty No.-1088, Pattenchery-121 Nos total 1317 nos of FHTC provided ( cc 1st billd FHTC-379 Nos ,2nd bill-1421 Nos,total billed-1800 Nos |
Chittur Project Dn - AE 1 |
|