Status Date |
Overall Project Status |
Project Officer |
Contact |
29 Dec 2022 |
Work in progress | 86% Completed | 29/12/2022
supply- 427.66 km and Total pipe laid 410 km total FHTC- no 9617os 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7974.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2440 No, Perumatty No.-3794, Pattenchery-3383 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
23 Dec 2022 |
Work in progress | 86% Completed | 23/12/2022
supply- 427.66 km and Total pipe laid 410 km total FHTC- 9478nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7974.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2370 No, Perumatty No.-3786, Pattenchery-3322 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
16 Dec 2022 |
Work in progress | 86% Completed | 16/12/2022
supply- 427.66 km and Total pipe laid 410 km total FHTC- 9359 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7974.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2281 No, Perumatty No.-3772, Pattenchery-3299 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
02 Dec 2022 |
Work in progress | 85% Completed | 02/12/2022
supply- 427.66 km and Total pipe laid 400 km total FHTC- 9129 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7974.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2127 No, Perumatty No.-3741, Pattenchery-3261 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
25 Nov 2022 |
Work in progress | 85% Completed | 25/11/2022
supply- 427.66 km and Total pipe laid 400 km total FHTC- 8930 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2005 No, Perumatty No.-3732, Pattenchery-3193 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
16 Nov 2022 |
Work in progress | 85% Completed | 16/11/2022
supply- 440 km and Total pipe laid 400 km total FHTC- 8795 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1922 No, Perumatty No.-3721, Pattenchery-3152 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
15 Nov 2022 |
Work in progress | 82% Completed | 15/11/2022
supply- 427.66 km and Total pipe laid 333.66 km total FHTC- 8795 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1922 No, Perumatty No.-3721, Pattenchery-3152 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
09 Nov 2022 |
Work in progress | 80% Completed | 09/11/2022
supply- 427.66 km and Total pipe laid 333.66 km total FHTC- 8672 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 142207 m supplied and 82418.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-4998M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-13398m supplied- 13244m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1861 No, Perumatty No.-3672, Pattenchery-3139 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
04 Nov 2022 |
Work in progress | 80% Completed | 04/11/2022
supply- 427.66 km and Total pipe laid 313.56 km total FHTC- 8546 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 142207 m supplied and 81928.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-4998M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-13398m supplied- 13094 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 7870.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1804 No, Perumatty No.-3630, Pattenchery-3112 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
28 Oct 2022 |
Work in progress | 80% Completed | 28/10/2022
supply- 427.66 km and Total pipe laid 309.520 km total FHTC- 8413 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 142207 m supplied and 79428.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-4998M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-13398m supplied- 13094 m laid, 8) 140 mm pvc -8 kg-4998 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 7870.50 m laid 11) 160mm 8kg 3810 m supplied -7788.50 m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-1741 No, Perumatty No.-3615, Pattenchery-3057 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820,5th bill-1922,total billed -5942No} |