Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Mar 2023 |
Work in progress | 91% Completed | 13/03/2023
supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10416nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2926No,/out of 4176 no Perumatty No.-3974,/out of 4744 nos p attenchery-3516/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
10 Mar 2023 |
Work in progress | 91% Completed | 10/03/2023 supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10416nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2926No,/out of 4176 no Perumatty No.-3974,/out of 4744 nos p attenchery-3516/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
05 Mar 2023 |
Work in progress | 91% Completed | 05/03/2023
supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10363nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2907 No,/out of 4176 no Perumatty No.-3945,/out of 4744 nos p attenchery-3511/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
17 Feb 2023 |
Work in progress | 91% Completed | 17/02/2023
supply- 427.66 km and Total pipe laid 416.433 km /out of 440km total FHTC- no 10359nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83000.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2117.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2907 No,/out of 4176 no Perumatty No.-3941,/out of 4744 nos p attenchery-3511/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
10 Feb 2023 |
Work in progress | 91% Completed | 10/02/2023
supply- 427.66 km and Total pipe laid 415.363km /out of 440km total FHTC- no 10242nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 82309 m laid 2).90mm pvc 6kg – 151969 m supplied and 83000.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1887.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2842 No,/out of 4176 no Perumatty No.-3893,/out of 4744 nos p attenchery-3507/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
03 Feb 2023 |
Work in progress | 90% Completed | 03/02/2023
supply- 427.66 km and Total pipe laid 414.869km /out of 440km total FHTC- no 10117 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 82309 m laid 2).90mm pvc 6kg – 151969 m supplied and 82820.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1743.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 370.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2772 No, Perumatty No.-3863, Pattenchery-3482 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
30 Jan 2023 |
Work in progress | 90% Completed | 30/01/2023
supply- 427.66 km and Total pipe laid 414.719km total FHTC- no 10074 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 82309 m laid 2).90mm pvc 6kg – 151969 m supplied and 82820.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 30097 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1713.10m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 370.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2749 No, Perumatty No.-3853, Pattenchery-3472 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
20 Jan 2023 |
Work in progress | 90% Completed | 20/01/2023
supply- 427.66 km and Total pipe laid 414.5035km total FHTC- no 9983 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 82309 m laid 2).90mm pvc 6kg – 151969 m supplied and 82820.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29923 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1671.10 m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 370.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly-2691No, Perumatty No.-3835, Pattenchery-3457 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
12 Jan 2023 |
Work in progress | 90% Completed | 12/01/2023
supply- 427.66 km and Total pipe laid 411.843km total FHTC- no 9832 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 81197 m laid 2).90mm pvc 6kg – 151969 m supplied and 82694.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29923 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5611 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9474.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1567.10 m laid 20) 125mm GI - 198 M supplied 95 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 135.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2589No, Perumatty No.-3815, Pattenchery-3428 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|
06 Jan 2023 |
Work in progress | 86% Completed | 06/01/2023
supply- 427.66 km and Total pipe laid 410.252km total FHTC- no 9731 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 80867 m laid 2).90mm pvc 6kg – 151969 m supplied and 82670.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 29875 m laid 4).110mm pvc 6 kg- 22002 m supplied – 14290.69 m laid 5)110mm 8kg-7398M supplied and 2940.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 5083 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9240.50 m laid 11) 160mm 8kg 3810 m supplied -7974.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8056.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 1530.10 m laid 20) 125mm GI - 198 M supplied 61 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 18.50m laid 23)150 mm GI 132 m supplied and 43.40m laid 24). Meenakshipuram tank-painting work completed , 25) FHTC Nallepilly-2516No, Perumatty No.-3805, Pattenchery-3410 { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} |
Chittur Project Dn - AE 1 |
|