Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 May 2023 Work in progress | 94% Completed | 26/05/2023 supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10822nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3208No,/out of 4176 no Perumatty No.-4032,/out of 4744 nos pattenchery-3582/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
18 May 2023 Work in progress | 94% Completed | 18/05/2023 supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10809nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3203No,/out of 4176 no Perumatty No.-4030,/out of 4744 nos pattenchery-3576/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
12 May 2023 supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10785nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3181No,/out of 4176 no Perumatty No.-4030,/out of 4744 nos pattenchery-3574/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
05 May 2023 Work in progress | 93% Completed | 05/05/2023 supply- 427.66 km and Total pipe laid 421.777 km /out of 440km total FHTC- no 10776nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 89820 m laid 2).90mm pvc 6kg – 151969 m supplied and 86286.50m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3172No,/out of 4176 no Perumatty No.-4030,/out of 4744 nos pattenchery-3574/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
28 Apr 2023 Work in progress | 93% Completed | 28/04/2023 supply- 427.66 km and Total pipe laid 420.559km /out of 440km total FHTC- no 10762nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 84159 m laid 2).90mm pvc 6kg – 151969 m supplied and 85428.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2637m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3167No,/out of 4176 no Perumatty No.-4021,/out of 4744 nos p attenchery-3574/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
21 Apr 2023 Work in progress | 92% Completed | 20/04/2023 supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10597nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3044No,/out of 4176 no Perumatty No.-4003,/out of 4744 nos p attenchery-3550/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
10 Apr 2023 Work in progress | 92% Completed | 10/04/2023 supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10597nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3044No,/out of 4176 no Perumatty No.-4003,/out of 4744 nos p attenchery-3550/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
30 Mar 2023 Work in progress | 92% Completed | 30/03/2023 supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10488nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2978No,/out of 4176 no Perumatty No.-3988,/out of 4744 nos p attenchery-3522/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
24 Mar 2023 Work in progress | 92% Completed | 24/03/2023 supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10416nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2926No,/out of 4176 no Perumatty No.-3974,/out of 4744 nos p attenchery-3516/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1
17 Mar 2023 Work in progress | 91% Completed | 17/03/2023 supply- 427.66 km and Total pipe laid 416.709km /out of 440km total FHTC- no 10427nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 83139 m laid 2).90mm pvc 6kg – 151969 m supplied and 83150.50 m laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13244m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6121 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2243.00m laid 20) 125mm GI - 198 M supplied 143 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 2930No,/out of 4176 no Perumatty No.-3981,/out of 4744 nos p attenchery-3516/ out of 5388 nos{ 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No} Chittur Project Dn - AE 1