Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Apr 2024 |
Work in progress | 96% Completed | 05/04/2024
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
15 Feb 2024 |
Work in progress | 96% Completed | 15/02/2024
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
24 Jan 2024 |
Work in progress | 96% Completed | 24/01/2024
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12058nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3811No,/out of 4176 no Perumatty No.-4353/out of 4744 nos pattenchery-3894/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
03 Jan 2024 |
Work in progress | 96% Completed | 03/01/2024
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12044 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3803 No,/out of 4176 no Perumatty No.-4351/out of 4744 nos pattenchery-3890/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
29 Nov 2023 |
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12044 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3803 No,/out of 4176 no Perumatty No.-4351/out of 4744 nos pattenchery-3890/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
26 Nov 2023 |
Work in progress | 95% Completed | 26/11/2023
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12044 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3803 No,/out of 4176 no Perumatty No.-4351/out of 4744 nos pattenchery-3890/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
09 Nov 2023 |
Work in progress | 95% Completed | 09/11/2023
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 12041 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3803 No,/out of 4176 no Perumatty No.-4350/out of 4744 nos pattenchery-3888/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
13 Oct 2023 |
Work in progress | 95% Completed | 13/10/2023
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 11970 nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3775 No,/out of 4176 no Perumatty No.-4336 /out of 4744 nos pattenchery-3859/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
28 Sep 2023 |
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 11937nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3775 No,/out of 4176 no Perumatty No.-4305 /out of 4744 nos pattenchery-3857/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|
06 Sep 2023 |
Work in progress | 95% Completed | 06/09/2023
supply- 440 km and Total pipe laid 435 km /out of 447km total FHTC- no 11771nos/out of 14308 nos 1).90mm pvc pipe -8kg- 89460 m supplied and 93240 m laid 2).90mm pvc 6kg – 151969 m supplied and 93132.50 laid 3).90mm pvc 10 kg-55158 m supplied and 330217m laid 4).110mm pvc 6 kg- 22002 m supplied – 14430.69 m laid 5)110mm 8kg-7398M supplied and 3704.50 m laid 6)110mm 10 kg -1556 m supplied and 285 M laid 7).140mm pvc-6 kg-16308m supplied- 13246m laid, 8) 140 mm pvc -8 kg-10266 m supplied – 6126 m laid 9)140mm pvc -10kg-300m supplied and 306 M laid 10) 160mm pvc 6 kg-13068 m supplied and 9762.50 m laid 11) 160mm 8kg 3810 m supplied -8172.50m laid 12) 200mm DI- 38049 m Supplied and 35526.65 m laid 13) 250mm DI- 13784 m Supplied and 13647.50m laid 14) 300mm DI pipe 11489m supplied -8122.70 m laid 15) 350mm DI- 3588.43 m supplied and 3587.24 m laid 16) 450mm DI – 3720.50m supplied and 4035.60m laid 17) 500mm DI-K9 pipe-250m supplied and 283.10m laid 18) 20 mm pvc 12.50 kg 1998 m supplied 19) 80mm GI pipe-2190m supplied 2649m laid 20) 125mm GI - 198 M supplied 156 m laid 21)160MM 10 KG-1002 m supplied and 898 m laid 22)100mm GI -300M supply and 400.50m laid 23)150 mm GI 132 m supplied and 162.90m laid 24). Meenakshipuram tank-painting work completed, 25) FHTC Nallepilly- 3704No,/out of 4176 no Perumatty No.-4236/out of 4744 nos pattenchery-3831/ out of 5388 nos { 1STbill-379, 2end bill-1421,3rd bill-1400, 4th bill-820, 5th bill-1922,total billed -5942No |
Chittur Project Dn - AE 1 |
|