Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
21 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
18 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
15 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
12 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
09 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
06 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
03 Apr 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
31 Mar 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2
28 Mar 2025 Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing Kannur WS Sn AE 2