Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
24 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted | Kannur WS Sn AE 2 | |
21 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted | Kannur WS Sn AE 2 | |
18 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted | Kannur WS Sn AE 2 | |
15 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted | Kannur WS Sn AE 2 | |
12 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing,3 rd & part bill submitted | Kannur WS Sn AE 2 | |
09 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
06 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
03 May 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
30 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 | |
27 Apr 2025 | Pipe laid 2700 m out of 2700 m and FHTC 963Nos out of 2500 Nos completed. Road restoration work completed, Tagging work under progressing | Kannur WS Sn AE 2 |