| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 15 May 2024 | Pipe laid 1000 m out of 2700 m and FHTC 140 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 12 May 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 09 May 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 06 May 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 03 May 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 30 Apr 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 27 Apr 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 | |
| 23 Apr 2024 | Pipe laid 738 m out of 2700 m and FHTC 120 Nos out of 2500 Nos completed. | Kannur WS Sn AE 2 |