| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 May 2024 | Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 15 May 2024 | Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 12 May 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 09 May 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 06 May 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 03 May 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 30 Apr 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 27 Apr 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 23 Apr 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 |