| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 772Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 14 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 768Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 11 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 768Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 08 Jul 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 05 Jul 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 02 Jul 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 29 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 26 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 23 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 20 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 |