| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 870 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 14 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 850 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 11 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 830 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 08 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 04 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 01 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 29 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 25 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 22 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 19 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 |