Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Apr 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
27 Apr 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
23 Apr 2024 | Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 |