| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 08 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 05 Dec 2024 | Pipe laid 2300 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 05 Dec 2024 | Pipe laid 2000 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 02 Dec 2024 | Pipe laid 2000 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 29 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 1050 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 26 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 23 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 21 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 18 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 | |
| 15 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress | Kannur WS Sn AE 2 |