| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 17 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 14 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 11 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 765Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 08 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 765Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 05 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 760 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 02 Jun 2024 | Pipe laid 950m out of 2300 m and FHTC 750 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 30 May 2024 | Pipe laid 950m out of 2300 m and FHTC 750 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 27 May 2024 | Pipe laid 950m out of 2300 m and FHTC 750 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 24 May 2024 | Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 21 May 2024 | Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 |