| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 12 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
| 09 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
| 06 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
| 03 Nov 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
| 31 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 980 Nos out of 2150 Nos completed,, Road restoration work in progress. | Kannur WS Sn AE 2 | |
| 28 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 950 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 25 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 22 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 20 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 17 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 |