Overall Project Status

Status Date Overall Project Status Project Officer Contact
29 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. Kannur WS Sn AE 2
26 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. Kannur WS Sn AE 2
23 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. Kannur WS Sn AE 2
20 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. Kannur WS Sn AE 2
17 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. Kannur WS Sn AE 2
14 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 768Nos out of 2150 Nos completed. Kannur WS Sn AE 2
11 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 765Nos out of 2150 Nos completed. Kannur WS Sn AE 2
08 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 765Nos out of 2150 Nos completed. Kannur WS Sn AE 2
05 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 760 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
02 Jun 2024 Pipe laid 950m out of 2300 m and FHTC 750 Nos out of 2150 Nos completed. Kannur WS Sn AE 2