Status Date Overall Project Status Project Officer Contact
26 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 890 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
26 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed 890 Kannur WS Sn AE 2
23 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed Kannur WS Sn AE 2
20 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed Kannur WS Sn AE 2
17 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 870 Nos out of 2150 Nos completed Kannur WS Sn AE 2
14 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 850 Nos out of 2150 Nos completed Kannur WS Sn AE 2
11 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 830 Nos out of 2150 Nos completed Kannur WS Sn AE 2
08 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed Kannur WS Sn AE 2
04 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed Kannur WS Sn AE 2
01 Sep 2024 Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed Kannur WS Sn AE 2