Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
26 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 890 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
26 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed 890 | Kannur WS Sn AE 2 | |
23 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
20 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
17 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 870 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
14 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 850 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
11 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 830 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
08 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
04 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
01 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 |