| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 13 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 10 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 07 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 800 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 04 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 780Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 01 Aug 2024 | Pipe laid 1575 m out of 2300 m and FHTC 772Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 29 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 772Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 26 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 772Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 23 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 772Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 20 Jul 2024 | Pipe laid 1575 m out of 2300 m and FHTC 772Nos out of 2150 Nos completed | Kannur WS Sn AE 2 |