Overall Project Status

Status Date Overall Project Status Project Officer Contact
30 May 2024 Pipe laid 950m out of 2300 m and FHTC 750 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
27 May 2024 Pipe laid 950m out of 2300 m and FHTC 750 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
24 May 2024 Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
21 May 2024 Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
18 May 2024 Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
15 May 2024 Pipe laid 950m out of 2300 m and FHTC 740 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
12 May 2024 Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
09 May 2024 Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
06 May 2024 Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. Kannur WS Sn AE 2
03 May 2024 Pipe laid 897 m out of 2300 m and FHTC 730 Nos out of 2150 Nos completed. Kannur WS Sn AE 2