| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 14 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 11 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 07 Oct 2024 | Pipe laid 2000 m out of 2300 m and FHTC 920 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 05 Oct 2024 | Pipe laid 1575 m out of 2300 m and FHTC 900 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 02 Oct 2024 | Pipe laid 1575 m out of 2300 m and FHTC 900 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 29 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 900 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 26 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 890 Nos out of 2150 Nos completed. | Kannur WS Sn AE 2 | |
| 26 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed 890 | Kannur WS Sn AE 2 | |
| 23 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 | |
| 20 Sep 2024 | Pipe laid 1575 m out of 2300 m and FHTC 880 Nos out of 2150 Nos completed | Kannur WS Sn AE 2 |