18 Feb 2025 132834 m pipe laid 427 HTC and 517FHTC Koothuparamba Proj AE 2
15 Feb 2025 132834 m pipe laid 427 HTC and 517FHTC Koothuparamba Proj AE 2
11 Feb 2025 132834 m pipe laid 427 HTC and 517FHTC Koothuparamba Proj AE 2
06 Feb 2025 132834 m pipe laid 427 HTC and 517FHTC Koothuparamba Proj AE 2
05 Feb 2025 132834 m pipe laid 427 HTC and 517FHTC Koothuparamba Proj AE 2
01 Feb 2025 132834 m pipe laid 427 HTC and 517FHTC Koothuparamba Proj AE 2
28 Jan 2025 132834 m pipe laid 441 HTC and 488 FHTC Koothuparamba Proj AE 2
24 Jan 2025 132834 m pipe laid 441 HTC and 488 FHTC Koothuparamba Proj AE 2
20 Jan 2025 132834 m pipe laid 449 HTC and 453 FHTC Koothuparamba Proj AE 2
10 Jan 2025 132834 m pipe laid 511 HTC and 347 FHTC Koothuparamba Proj AE 2