Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
18 Dec 2024 | 132834 m pipe laid 504 HTC and 281 FHTC | Koothuparamba Proj AE 2 | |
13 Dec 2024 | 130000 m pipe laid 543HTC 182 FHTCS | Koothuparamba Proj AE 2 | |
10 Dec 2024 | 130000 m pipe laid 543HTC 182 FHTCS | Koothuparamba Proj AE 2 | |
05 Dec 2024 | 130000 m pipe laid 543HTC 182 FHTCS | Koothuparamba Proj AE 2 | |
28 Nov 2024 | 130000 m pipe laid 860 HTC 157 FHTCS | Koothuparamba Proj AE 2 | |
23 Nov 2024 | 128000 m pipe laid 860 HTC 157 FHTCS | Koothuparamba Proj AE 2 | |
19 Nov 2024 | 128000 m pipe laid 860 HTC 157 FHTCS | Koothuparamba Proj AE 2 | |
14 Nov 2024 | 128000 m pipe laid 860 HTC 157 FHTCS | Koothuparamba Proj AE 2 | |
07 Nov 2024 | 128000 m pipe laid 860 HTC 157 FHTCS | Koothuparamba Proj AE 2 | |