| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 28 Dec 2020 | RWPM-20.984 km pipe laying completed | Nattika Project Dn AE 6 | |
| 27 Dec 2020 | Intake well - Civil work completed. Electrical works and erection of transformer in going on. 15MLD WTP at Kottapadi - Civil Structure work completed. Electromechanical works and Finishing works is going on. | Nattika Project Dn AE 5 | |
| 21 Dec 2020 | Intake well - Civil work completed. Electrical works and erection of transformer in going on. 15MLD WTP at Kottapadi - Civil Structure work completed. Electromechanical works and Finishing works is going on. | Nattika Project Dn AE 5 | |
| 20 Dec 2020 | RWPM-20.704 km pipe laying completed | Nattika Project Dn AE 6 | |
| 14 Dec 2020 | RWPM-20.473 km pipe laying completed | Nattika Project Dn AE 6 | |
| 13 Dec 2020 | Intake well - Civil work completed. Electrical works and erection of transformer in going on. 15MLD WTP at Kottapadi - Civil Structure work completed. Electromechanical works and Finishing works is going on. | Nattika Project Dn AE 5 | |
| 04 Dec 2020 | RWPM-20.468 km pipe laying completed | Nattika Project Dn AE 6 | |
| 04 Dec 2020 | Intake well - Civil work completed. Electrical works and erection of transformer in going on. 15MLD WTP at Kottapadi - Civil Structure work completed. Electromechanical works and Finishing works is going on. | Nattika Project Dn AE 5 | |
| 28 Nov 2020 | RWPM-20.115 km pipe laying completed | Nattika Project Dn AE 6 | |
| 27 Nov 2020 | Intake well - Civil work completed. Electrical works and erection of transformer in going on. 15MLD WTP at Kottapadi - Civil Structure work completed. Electromechanical works and Finishing works is going on. | Nattika Project Dn AE 5 |