Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Feb 2024 |
Pipe line laying in Causeway road is started (320m laid). 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, clay jali window masonry work progress & boundary Wall earthwork progress. Electro-mechanical work is ongoing. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - column 1st lift concrete work completed, Approach bridge plastering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Project Dn EE |
|
14 Feb 2024 |
Pipe line laying in Causeway road is started (320m laid). 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, clay jali window masonry work progress & boundary Wall earthwork progress. Electro-mechanical work is ongoing. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - column 1st lift concrete work completed, Approach bridge plastering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
08 Feb 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, clay jali window masonry work progress & boundary Wall earthwork progress. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - column 1st lift concrete work completed, Approach bridge plastering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
31 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, clay jali window masonry work progress & boundary Wall earthwork progress. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - column 1st lift concrete work completed, Approach bridge plastering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
30 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, clay jali window masonry work progress & boundary Wall earthwork progress. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - column 1st lift concrete work completed, Approach bridge plastering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.
|
Palakkad Proj Dn AE 4 |
|
29 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, clay jali window masonry work progress & boundary Wall earthwork progress. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - column 1st lift concrete work completed, Approach bridge plastering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.
|
Palakkad Proj Dn AE 4 |
|
27 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - gantry beam concrete completed, column 1st lift concrete work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.
|
Palakkad Proj Dn AE 4 |
|
25 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, bridge mechanical work on going. Intake well (6 m dia) cum pump house - gantry beam concrete completed, column 1st lift concrete work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.
|
Palakkad Proj Dn AE 4 |
|
24 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, mechanical work on going. Intake well (6 m dia) cum pump house - gantry beam concrete completed, column 1st lift concrete work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.
|
Palakkad Proj Dn AE 4 |
|
23 Jan 2024 |
125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, mechanical work on going. Intake well (6 m dia) cum pump house - gantry beam concrete completed, column steel work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|