Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
26 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel cover slab work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -cover slab steel work on going. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going ,HTC -4641/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
23 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel cover slab work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work completed. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going ,HTC -4641/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
22 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel cover slab work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work completed. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going ,HTC -4641/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
21 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work completed. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going ,HTC -4641/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
20 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- clariflocculator sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work completed. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going .HTC -4641/5928 completed Palakkad Proj Dn AE 4
19 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- clariflocculator sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work completed. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going .HTC -4641/5928 completed Palakkad Proj Dn AE 4
18 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- clariflocculator sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work completed. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going .HTC -4641/5928 completed Palakkad Proj Dn AE 4
16 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- clariflocculator sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work on going. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going .HTC -4594/5928 completed Palakkad Proj Dn AE 4
15 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- clariflocculator sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift concrete work on going. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going .HTC -4594/5928 completed Palakkad Proj Dn AE 4
14 Dec 2023 123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- clariflocculator sludge chamber concrete completed, Intake well (6 m dia) cum pump house - Approach Bridge concrete completed,5 LL OHSR -floor slab concrete completed, side wall 4th lift shuttering work on going. 10 LL OHSR: cover slab concrete completed, celling & inside plastering on going .HTC -4594/5928 completed Palakkad Proj Dn AE 4