Status Date Overall Project Status Project Officer Contact
22 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, mechanical work on going. Intake well (6 m dia) cum pump house - brick work completed, gantry beam concrete on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
20 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, mechanical work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, mechanical work on going. Intake well (6 m dia) cum pump house - brick work completed, ring beam shuttering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
19 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, mechanical work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, mechanical work on going. Intake well (6 m dia) cum pump house - brick work completed, ring beam shuttering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
18 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work 80% completed, mechanical work on going. Filter bed: plastering work & tile work completed, Aerator: plastering on going. clariflocculator- structural work completed, mechanical work on going. Intake well (6 m dia) cum pump house - brick work completed, ring beam shuttering work on going. 5 LL OHSR -structural work completed, plastering work on going. 10 LL OHSR: structural work completed, plastering on going.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
17 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed. Intake well (6 m dia) cum pump house - brick work completed, lintel & sunshade shuttering work on going. 5 LL OHSR -parapet wall completed, plastering work on going. 10 LL OHSR: celling & out side plastering on going ,HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
16 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed. Intake well (6 m dia) cum pump house - brick work completed, lintel & sunshade shuttering work on going. 5 LL OHSR -parapet wall completed, plastering work on going. 10 LL OHSR: celling & out side plastering on going ,HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj AE 3
12 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed. Intake well (6 m dia) cum pump house - brick work completed, lintel & sunshade shuttering work on going. 5 LL OHSR -parapet wall completed, plastering work on going. 10 LL OHSR: celling & out side plastering on going ,HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
11 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed. Intake well (6 m dia) cum pump house - brick work completed, lintel & sunshade shuttering work on going. 5 LL OHSR -parapet wall completed, plastering work on going. 10 LL OHSR: celling & out side plastering on going ,HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
10 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel cover slab work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed, Intake well (6 m dia) cum pump house - brick work completed, lintel & sunshade shuttering work on going. 5 LL OHSR -parapet wall completed, plastering work on going. 10 LL OHSR: celling & out side plastering on going ,HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4
09 Jan 2024 125.53/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel cover slab work on going. Filter bed: plastering work & tile work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress, clariflocculator- sludge chamber concrete completed, Intake well (6 m dia) cum pump house - brick work completed, lintel & sunshade shuttering work on going. 5 LL OHSR -cover slab steel work on going. 10 LL OHSR: cover slab concrete completed, celling & out side plastering on going ,HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. Palakkad Proj Dn AE 4