Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Jun 2024 |
Pipe line laying in Causeway road. 136.1348/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -Painting work ongoing. Structure and Plastering work completed. 5176/5928 completed,5039 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
04 Jun 2024 |
Pipe line laying in Causeway road. 136.1348/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -Painting work ongoing. Structure and Plastering work completed. 5176/5928 completed,5039 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
04 Jun 2024 |
Pipe line laying in Causeway road. 136.1348/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -Painting work ongoing. Structure and Plastering work completed. 5176/5928 completed,5039 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
03 Jun 2024 |
Pipe line laying in Causeway road. 136.1348/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -Painting work ongoing. Structure and Plastering work completed. 5176/5928 completed,5019 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
01 Jun 2024 |
Pipe line laying in Causeway road. 136.1348/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -Pumphouse painting ongoing. Structure and Plastering work completed. 5176/5928 completed,5019 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
31 May 2024 |
Pipe line laying in Causeway road. 135.8198/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -Pumphouse painting ongoing. Structure and Plastering work completed. 5176/5928 completed,5019 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
29 May 2024 |
Pipe line laying in Causeway road. 135.8198/169.845 km completed. WTP - Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -Pumphouse painting ongoing. Structure and Plastering work completed. 5176/5928 completed,5019 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
28 May 2024 |
Pipe line laying in Causeway road. 135.4768/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 5052/5928 completed,5019 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
27 May 2024 |
Pipe line laying in Causeway road. 135.4768/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 5052/5928 completed,5019 nos geo tagged. |
Palakkad Project Dn AE |
|
24 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4685/5928 completed,4625 nos geo tagged. |
Palakkad Project Dn EE |
|