Status Date |
Overall Project Status |
Project Officer |
Contact |
30 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
26 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
25 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
23 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
22 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
20 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
19 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
18 Mar 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail 90% completed.Clariflocculator- structural work completed & bridge work completed. Aluminium fabrication work on goimg.. 5 LL OHSR -structural work completed, plastering 50% completed.10 LL OHSR: structural work completed, plastering 85% completed.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Project Dn EE |
|
14 Mar 2024 |
Pipe line laying in Causeway road on going. 128.35/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail 90% completed.Clariflocculator- structural work completed & bridge work completed. Aluminium fabrication work on goimg.. 5 LL OHSR -structural work completed, plastering 50% completed.10 LL OHSR: structural work completed, plastering 85% completed.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Project Dn AE |
|
06 Mar 2024 |
Pipe line laying in Causeway road on going. 128.35/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail 90% completed.Clariflocculator- structural work completed & bridge work completed. Aluminium fabrication work on goimg.. 5 LL OHSR -structural work completed, plastering 50% completed.10 LL OHSR: structural work completed, plastering 85% completed.HTC -4645/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|