Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR -handrail work & pumphouse lintel above brick work,Machanical & Electrical work to be contected. |
Palakkad Proj Dn AE 4 |
|
16 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -handrail work & Pumphouse brick masonry,Machanical & Electrical work to be contected.Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR:Painting work on going, structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
15 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Pumphouse brick masonry,Machanical & Electrical work to be contected.Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR:Painting work on going, structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
12 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -staircase plasterwork,Machanical & Electrical work to be contected.Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR:Painting work on going, structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
11 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -staircase plasterwork,Machanical & Electrical work to be contected.Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR:Painting work on going, structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
08 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical work starts,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -staircase plasterwork,Machanical & Electrical work to be contected.Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
06 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed.
5 LL OHSR -Machanical & Electrical work to be contected.Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.GI gap welding odanur parali road (right side) |
Palakkad Proj Dn AE 4 |
|
03 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Pebbles Cleaning Work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued.GI gap welding odanur parali road (right side) |
Palakkad Proj Dn AE 4 |
|
02 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed.
WTP- Pebbles Cleaning Work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,4625 nos geo tagged,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|
01 Apr 2024 |
Pipe line laying in Causeway road on going. 128.81/169.845 km completed. WTP- structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed, Aluminium fabrication work completed. 5 LL OHSR -Cleaning work going,structural work completed, plastering completed,Cleaning work going.10 LL OHSR: structural work completed, plastering completed,painting on going.HTC -4651/5928 completed,PWD road cutting permission ( major ramaswami road, vavulliyal -palakkad road) not issued. |
Palakkad Proj Dn AE 4 |
|