Status Date |
Overall Project Status |
Project Officer |
Contact |
20 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4685/5928 completed,4625 nos geo tagged. |
Palakkad Project Dn EE |
|
15 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4685/5928 completed,4625 nos geo tagged. |
Palakkad Project Dn EE |
|
08 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
06 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - filterhouse & washwater Chanel PCC. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
04 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel Earth work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
02 May 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Wash outlet channel Earth work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. Clariflocculator - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
30 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. Clariflocculator - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
29 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works ongoing,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Gantry crane Beam work,Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work,Machanical & Electrical work to be contected.Structure and Plastering work completed, Cleaning work done.HTC - 4651/5928 completed,4625 nos geo tagged |
Palakkad Project Dn EE |
|
22 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Gantry crane Beam work,Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work,Machanical & Electrical work to be contected.Structure and Plastering work completed, Cleaning work done.HTC - 4651/5928 completed,4625 nos geo tagged |
Palakkad Project Dn EE |
|
17 Apr 2024 |
Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR -handrail work & pumphouse lintel above brick work,Machanical & Electrical work to be contected.Structure and Plastering work completed, Cleaning work done.HTC - 4651/5928 completed,4625 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|