Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 May 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4685/5928 completed,4625 nos geo tagged. Palakkad Project Dn EE
15 May 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4685/5928 completed,4625 nos geo tagged. Palakkad Project Dn EE
08 May 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel steel work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. Palakkad Proj Dn AE 4
06 May 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - filterhouse & washwater Chanel PCC. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. Palakkad Proj Dn AE 4
04 May 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP - Wash outlet channel Earth work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. Palakkad Proj Dn AE 4
02 May 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Wash outlet channel Earth work. Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. Clariflocculator - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. Palakkad Proj Dn AE 4
30 Apr 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. Clariflocculator - painting completed. Intake well-Gantry crane Beam work in progress, Plastering completed, Aluminum fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work ongoing. Structure and Plastering work completed, Cleaning work ongoing. HTC - 4651/5928 completed,4625 nos geo tagged. Palakkad Proj Dn AE 4
29 Apr 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works ongoing,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Gantry crane Beam work,Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work,Machanical & Electrical work to be contected.Structure and Plastering work completed, Cleaning work done.HTC - 4651/5928 completed,4625 nos geo tagged Palakkad Project Dn EE
22 Apr 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Gantry crane Beam work,Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR ODANUR -handrail work & pumphouse plastering work,Machanical & Electrical work to be contected.Structure and Plastering work completed, Cleaning work done.HTC - 4651/5928 completed,4625 nos geo tagged Palakkad Project Dn EE
17 Apr 2024 Pipe line laying in Causeway road. 128.81/169.845 km completed. WTP- Mechanical and Electrical works started,filterbed gravel filling work ,structural work 90% completed,Clay jally work completed,compound wall 90% completed,electrical work on going.Plastering ,tileing completed,painting work on going.Hand rail completed.Clariflocculator- painting on going.Intake well-Plastering completed,Machanical & Electrical work to be contected. Aluminium fabrication work completed. 5 LL OHSR -handrail work & pumphouse lintel above brick work,Machanical & Electrical work to be contected.Structure and Plastering work completed, Cleaning work done.HTC - 4651/5928 completed,4625 nos geo tagged. Palakkad Proj Dn AE 4