Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Jun 2024 |
Pipe line laying 136.1348/169.845 km completed. WTP - Plumping, Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 96% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work almost completed. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -mechanical work ( column pipe DI setting )ongoing & operator room door & window fixing work. Structure ,Plastering & painting work completed. 5232/5928 completed 51611 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
22 Jun 2024 |
Pipe line laying 136.1348/169.845 km completed. WTP - Plumping, Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -mechanical work ( column pipe DI setting )ongoing & operator room door & window fixing work. Structure ,Plastering & painting work completed. 5232/5928 completed 51611 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
20 Jun 2024 |
Pipe line laying 136.1348/169.845 km completed. WTP - Plumping, Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -mechanical work ( column pipe DI setting )ongoing. Structure ,Plastering & painting work completed. 5232/5928 completed 51611 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
18 Jun 2024 |
Pipe line laying 136.1348/169.845 km completed. WTP - Plumping, Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -Painting work ongoing. Structure and Plastering work completed. 5232/5928 completed 5141 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|
14 Jun 2024 |
Pipe line laying 136.1348/169.845 km completed. WTP - Plumping, Mechanical and Electrical works ongoing, filter bed gravel filling work completed, structural work 90% completed, Clay jally work completed, compound wall 90% completed, electrical work on going. Plastering ,tiling completed, painting work on going. Hand rail completed. CLARIFLOCCULATOR - Painting completed. Intake well- Plastering completed, Painting almost completed, Aluminum fabrication work completed.10 LL OHSR - Mechanical work ongoing. 5 LL OHSR ODANUR -Painting work ongoing. Structure and Plastering work completed. 5176/5928 completed,5060 nos geo tagged. |
Palakkad Proj Dn AE 4 |
|