Status Date |
Overall Project Status |
Project Officer |
Contact |
23 Sep 2023 |
116.08 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam completed,column concrete on going.10 LL OHSR: cover slab form work on going.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
21 Sep 2023 |
115.25 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC completed. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam concrete work on going.10 LL OHSR: cover slab form work on going.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
20 Sep 2023 |
114.95 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam shuttering work on going.10 LL OHSR: fourth lift concrete work completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
19 Sep 2023 |
114.95 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam shuttering work on going.10 LL OHSR: fourth lift concrete work completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
17 Sep 2023 |
114.95 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam shuttering work on going.10 LL OHSR: fourth lift concrete work completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
18 Sep 2023 |
114.95 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam shuttering work on going.10 LL OHSR: fourth lift concrete work completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
17 Sep 2023 |
114.95 km/169.845 km completed. WTP- structural work completed, mechanical work on going,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,approach bridge earth work progress,pumphouse column steel work progress. 5 LL OHSR -3rd brace beam shuttering work on going.10 LL OHSR: fourth lift concrete work completed.RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
15 Sep 2023 |
114.01 km/169.845 km completed. WTP- structural work completed,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,pumphouse column steel work progress. 5 LL OHSR -second brace beam concrete completed, column concrete completed.10 LL OHSR: third lift of side wall completed.fourth lift shutering work progress .RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
14 Sep 2023 |
114.01 km/169.845 km completed. WTP- structural work completed,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,pumphouse column steel work progress. 5 LL OHSR -second brace beam concrete completed, column concrete completed.10 LL OHSR: third lift of side wall completed.fourth lift shutering work progress .RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|
13 Sep 2023 |
113.08 km/169.845 km completed. WTP- structural work completed,Aerator: 4th lift centre shaft RCC on going. Intake well (6 m dia)-upto floor slab completed,pumphouse column steel work progress. 5 LL OHSR -second brace beam concrete completed, column rising on going.10 LL OHSR: third lift of side wall completed.fourth lift shutering work progress .RWPM: 300 M to be laid.CWPM: 1.5 km to be laid. HTC(4305) completed. |
Palakkad Proj Dn AE 4 |
|