Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Nov 2023 |
123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water and clear water Chanel shuttering work progress, Filter bed: plastering work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed, column 1 st lift concrete on going, 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed,celling plastering on going .HTC -4485/5928 completed |
Palakkad Proj Dn AE 4 |
|
10 Nov 2023 |
123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, raw water Chanel shuttering work progress, Filter bed: plastering work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed, column 1 st lift concrete on going, 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4480/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
09 Nov 2023 |
123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed, column 1 st lift concrete on going, 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4470/5928 completed. |
Palakkad Proj Dn AE 4 |
|
08 Nov 2023 |
123.55 km/169.845 km (RWPM: 300 M to be laid. CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed, column 1 st lift concrete on going, 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4470/5928 completed. |
Palakkad Proj Dn AE 4 |
|
07 Nov 2023 |
123.55 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift concrete completed, plastering work on going. Flash mixer steel & shuttering work progress. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed, column 1 st lift concrete on going, 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4470/5928 completed. |
Palakkad Proj Dn AE 4 |
|
06 Nov 2023 |
123.18 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift concrete completed, Flash mixer steel & shutering work progress. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed,column 1 st lift concrete on going, 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4470/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
04 Nov 2023 |
123.18 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift concrete completed. Intake well (6 m dia) cum pump house - Approach Bridge brace beam concrete completed. 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4470/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
03 Nov 2023 |
122.86 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4463/5928 completed.
|
Palakkad Proj Dn AE 4 |
|
02 Nov 2023 |
122.86 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4463/5928 completed. |
Palakkad Proj Dn AE 4 |
|
01 Nov 2023 |
122.86 km/169.845 km (RWPM: 300 M to be laid.CWPM: 1.5 km to be laid.) completed. WTP- structural work completed, mechanical work on going, Filter bed: plastering work on going, Aerator: 5th lift shuttering on going. Intake well (6 m dia) cum pump house - Bracebeam shutering work on progress. 5 LL OHSR -floor slab & beam steel work progress. 10 LL OHSR: cover slab concrete completed. HTC -4463/5928 completed. |
Palakkad Proj Dn AE 4 |
|